4202 E WILLIMET AVE 90039
Certificate Information: 4202 E WILLIMET AVE 90039
- Application / Permit
- 22010-30000-05783
- Plan Check / Job No.
- B22WL04354
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story SFD w./ att. 1-car garage at middle of the lot
- Permit Issued
- Issued on 7/5/2023
- Issuing Office
- Current Status
- CofO Issued on 2/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | REZA HAGHIGHAT |
| Corrections Issued | 12/10/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 12/12/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/14/2022 | APPLICANT |
| Plan Check Approved | 2/17/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 7/3/2023 | REZA HAGHIGHAT |
| Issued | 7/5/2023 | APPLICANT |
| CofO in Progress | 2/5/2025 | THOMAS LOGRASSO |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| CofO Issued | 2/9/2025 | DEROLD HAUFF |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2022 | AMAAN MALIK |
| Highway dedication | Cleared | 12/27/2022 | AMAAN MALIK |
| Miscellaneous | Cleared | 12/28/2022 | DANIEL CORONADO |
| Frnt yard landscape/Water mgmt | Cleared | 12/29/2022 | DANIEL CORONADO |
| ZI | Cleared | 12/29/2022 | DANIEL CORONADO |
| Low Impact Development | Cleared | 1/12/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/17/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 2/2/2023 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 2/8/2023 | MATTHEW CRAIG |
| SB8 RUD | Cleared | 4/18/2023 | JAMES MCCARTHY |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/19/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 9/19/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/29/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 10/2/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 5/10/2024 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 7/26/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 7/26/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 7/30/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/6/2024 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 8/6/2024 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 8/6/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 8/14/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 8/27/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/12/2024 | Approved | THOMAS LOGRASSO |
| Shower Pan | 9/12/2024 | Approved | THOMAS LOGRASSO |
| Sewer | 10/22/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 10/22/2024 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 10/31/2024 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 1/28/2025 | Conditional Approval | THOMAS LOGRASSO |
| HVAC-Final | 1/28/2025 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 1/30/2025 | Approved | THOMAS LOGRASSO |
| Final | 1/30/2025 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 1/30/2025 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Not Required | THOMAS LOGRASSO |
| Smoke Detectors | 1/30/2025 | Approved | THOMAS LOGRASSO |
| Final | 2/4/2025 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 2/4/2025 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 2/4/2025 | Approved | THOMAS LOGRASSO |