439 W 71ST ST 90003
Certificate Information: 439 W 71ST ST 90003
- Application / Permit
- 22010-30000-05630
- Plan Check / Job No.
- B22WL04268
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- construction of ADU over garage at rear. (Bldg B)
- Permit Issued
- Issued on 3/21/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | KAVIAN REFAHI |
| Corrections Issued | 12/15/2022 | KAVIAN REFAHI |
| Quality Review Completed | 12/19/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 3/10/2023 | KAVIAN REFAHI |
| Issued | 3/21/2023 | APPLICANT |
| CofO in Progress | 1/5/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/26/2024 | DEROLD HAUFF |
| CofO Issued | 1/26/2024 | DEROLD HAUFF |
| Permit Finaled | 1/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 12/22/2022 | KENNETH LE |
| Address approval | Cleared | 12/28/2022 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2022 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/28/2022 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 1/19/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/20/2023 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 2/22/2023 | NADER ISKANDER |
| Hydrant and Access approval | Cleared | 2/22/2023 | KURT CORRAL |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD 900 LOS ANGELES, CA 90064 |
| Contractor | Moreno Chris; Lic. No.: 973501-B | 1158 W 126TH STREET LOS ANGELES, CA 90044 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/26/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/8/2023 | Approved | MICHAEL LEWIS |
| Wood Frame | 5/8/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/15/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 6/15/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/16/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/16/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/16/2023 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 6/16/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 6/16/2023 | Approved | MICHAEL LEWIS |
| Insulation | 6/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/7/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/7/2023 | Approved | MICHAEL LEWIS |
| Sewer | 8/22/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/22/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 12/20/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 12/20/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/21/2023 | Approved | MICHAEL LEWIS |
| Final | 12/21/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 12/21/2023 | Approved | MICHAEL LEWIS |
| MERV13>=Final | 12/21/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 12/21/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 12/21/2023 | Approved | MICHAEL LEWIS |
| Final | 12/29/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 1/4/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/4/2024 | Approved | ALEJANDRO DE ARTOLA |