1020 N PIONEER AVE 90744
Certificate Information: 1020 N PIONEER AVE 90744
- Application / Permit
- 22010-30000-05549
- Plan Check / Job No.
- B22WL04205
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- detached garage. *** 2 of 2 ***
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Current Status
- CofO Issued on 5/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | KAVIAN REFAHI |
| Corrections Issued | 12/19/2022 | KAVIAN REFAHI |
| Quality Review Completed | 12/27/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/6/2023 | APPLICANT |
| Plan Check Approved | 8/9/2023 | KAVIAN REFAHI |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 4/29/2026 | EUGENE CASSIDY |
| Permit Finaled | 5/1/2026 | ANSON MAGLASANG |
| CofO Issued | 5/1/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/1/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/23/2023 | KENTON TRINH |
| ZA Case | Cleared | 1/23/2023 | KENTON TRINH |
| ZI | Cleared | 1/23/2023 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | ANA SORIANO |
| Abandoned oil well | Cleared | 3/16/2023 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 3/16/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 4/13/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 4/13/2023 | ANA SORIANO |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Platinum Pacific Construction Inc; Lic. No.: 1087563-B | 2708 WILSHIRE BLVD #468 SANTA MONICA, CA 90403 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 5/23/2024 | Conditional Approval | ANSON MAGLASANG |
| METHANE-Subgrade | 5/30/2024 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Partial Approval | EUGENE CASSIDY |
| METHANE-Subgrade | 6/18/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Methane Barrier | 6/26/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Methane Barrier | 6/27/2024 | Partial Approval | EUGENE CASSIDY |
| METHANE-Barrier | 6/28/2024 | Approved | EUGENE CASSIDY |
| Deputy Methane Barrier | 7/22/2024 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/22/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 7/22/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Partial Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/21/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 2/21/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 2/21/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/5/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/21/2025 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 4/21/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 4/23/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/13/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/23/2025 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Final | 10/31/2025 | Approved | EUGENE CASSIDY |
| Grounding or Bonding | 10/31/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | EUGENE CASSIDY |
| Final | 4/28/2026 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 4/28/2026 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/28/2026 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Not Required | EUGENE CASSIDY |
| Service/Power Release | 4/28/2026 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 4/28/2026 | Approved | EUGENE CASSIDY |