17961 W MEDLEY DR 91316

Certificate Information: 17961 W MEDLEY DR 91316

Application / Permit
22010-30000-05380
Plan Check / Job No.
B22WL04093
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
patio trellis and pool bath *** 2 of 4 ***
Permit Issued
Issued on 1/20/2023
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 KAVIAN REFAHI
Corrections Issued 11/14/2022 KAVIAN REFAHI
Quality Review Completed 11/28/2022 CHIHARU SUZUKI
Building Plans Picked Up 11/29/2022 APPLICANT
Plan Check Approved 1/19/2023 KAVIAN REFAHI
Issued 1/20/2023 APPLICANT
CofO in Progress 4/5/2024 JOHN KIDWELL
Permit Finaled 4/15/2024 JOHN JANSON
CofO Issued 4/15/2024 JOHN JANSON
Permit Finaled 4/15/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/21/2022 FERNANDO GIL
Roof/Waste drainage to street Cleared 12/21/2022 FERNANDO GIL
ZA Case Cleared 12/27/2022 BRENNEN OBETO
Hydrant and Access approval Cleared 1/11/2023 GILBERT URREA
Grading Pre-Inspection Cleared 1/19/2023 KAVIAN REFAHI

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 3/20/2023 Partial Approval DAVID SANDOVAL
Deputy Other (see comments) 6/26/2023 Approved SEAN HAUPT
Piling/Pier/Caisson 6/26/2023 Partial Approval SEAN HAUPT
Deputy Other (see comments) 6/28/2023 Approved SEAN HAUPT
Deputy Reinf. Concrete 6/28/2023 Approved SEAN HAUPT
PLUMBING-Rough 7/13/2023 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 7/20/2023 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 7/20/2023 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 8/10/2023 Approved JEFFREY PARD
Footing/Foundation/Slab 8/10/2023 Approved JEFFREY PARD
Deputy Reinf. Concrete 8/11/2023 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 9/21/2023 Approved JEFFREY PARD
Verify Sprinkler Sign Off 9/21/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 9/22/2023 Approved JEFFREY PARD
HVAC-Rough 9/22/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 9/22/2023 Approved JEFFREY PARD
PLUMBING-Rough 9/22/2023 Approved JEFFREY PARD
Final 3/28/2024 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved JOHN KIDWELL
Service/Power Release 3/28/2024 Approved JOHN KIDWELL
Smoke Detectors 3/28/2024 Approved JOHN KIDWELL
Final 4/2/2024 OK to Issue CofO JOHN KIDWELL