10403 S HICKORY ST 90002

Certificate Information: 10403 S HICKORY ST 90002

Application / Permit
22010-30000-05368
Plan Check / Job No.
B22WL04077
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 2-story S.F.D. in front *** 1 of 3 ***
Permit Issued
Issued on 2/15/2024
Issuing Office
Metro
Current Status
Issued on 2/15/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/8/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 KAVIAN REFAHI
Corrections Issued 11/14/2022 KAVIAN REFAHI
Quality Review Completed 11/28/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/8/2022 APPLICANT
Plan Check Approved 2/1/2023 KAVIAN REFAHI
Issued 2/15/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/28/2022 CINDY QI
Hydrant and Access approval Cleared 12/12/2022 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 12/19/2022 CINDY QI
Sewer availability Cleared 12/19/2022 CINDY QI
Low Impact Development Cleared 1/19/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/23/2023 CINDY QI

Contact Information

Architect Hamid, Dehghan; Lic. No.: C35150 2355 WESTWOOD BLVD   # 900    LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2024 Not Ready for Inspection BEN MOLSTAD
Underground Mechanical 3/15/2024 Not Ready for Inspection BEN MOLSTAD
Deputy Reinf. Concrete 4/12/2024 Conditional Approval JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 8/16/2024 Partial Approval BEN MOLSTAD
PLUMBING-Rough 8/16/2024 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 9/4/2024 Approved BEN MOLSTAD
PLUMBING-Rough 9/4/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Approved BARRY HACHE
Sewer 12/27/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 4/2/2025 Approved ANTHONY EGSON
HVAC-Rough 4/2/2025 Approved ANTHONY EGSON
PLUMBING-Rough 4/2/2025 Approved ANTHONY EGSON
HVAC-Rough 4/8/2025 Approved ANTHONY EGSON
HVAC-Rough 4/15/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Corrections Issued ANTHONY EGSON