212-212 1/2 E 29TH ST 90011
Certificate Information: 212-212 1/2 E 29TH ST 90011
- Application / Permit
- 22010-30000-05364
- Plan Check / Job No.
- B22WL04063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- new 3-story Duplex with attached garage in front *** 2 of 2 ***
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | KAVIAN REFAHI |
| Corrections Issued | 11/28/2022 | KAVIAN REFAHI |
| Quality Review Completed | 12/6/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/14/2022 | APPLICANT |
| Applicant returned to address corrections | 3/6/2023 | KAVIAN REFAHI |
| Plan Check Approved | 3/23/2023 | KAVIAN REFAHI |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 6/25/2024 | ALEJANDRO DE ARTOLA |
| CofO Issued | 7/10/2024 | DEROLD HAUFF |
| Permit Finaled | 7/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 12/1/2022 | DORIS KWOK |
| Frnt yard landscape/Water mgmt | Cleared | 1/9/2023 | NATHAN ROMINE |
| Miscellaneous | Cleared | 1/9/2023 | NATHAN ROMINE |
| Address approval | Cleared | 1/10/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/27/2023 | AMAAN MALIK |
| Low Impact Development | Cleared | 2/6/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/13/2023 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 2/14/2023 | GILBERT URREA |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD 900 LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 5/11/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Underground Mechanical | 5/11/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 8/31/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/21/2023 | Approved | JUSTIN HAWLEY |
| Green Building Final | 9/21/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 9/21/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 9/21/2023 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/5/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/18/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/22/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 2/29/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 5/1/2024 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Final | 5/1/2024 | Not Ready for Inspection | DAVID FEILER |
| Gas Test | 5/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 5/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 5/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 5/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/24/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |