- new 3-story S.F.D. in middle *** 2 of 3 ***
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | YASHAR EMAMI |
| Corrections Issued | 10/13/2022 | YASHAR EMAMI |
| Quality Review Completed | 10/22/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 10/24/2022 | APPLICANT |
| Applicant returned to address corrections | 1/26/2023 | YASHAR EMAMI |
| Plan Check Approved | 2/13/2023 | YASHAR EMAMI |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 6/14/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 6/20/2024 | RUBEN SALAS |
| CofO Issued | 6/20/2024 | RUBEN SALAS |
| Permit Finaled | 6/20/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/7/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 11/19/2022 | RUEL COLE |
| Low Impact Development | Cleared | 1/4/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/4/2023 | LEE GUILBEAUX |
| SB8 RUD | Cleared | 3/2/2023 | SALLY LIANG |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 3/28/2023 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 4/6/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 10/25/2023 | Approved | ROBERT GOLD |
| HVAC-Rough | 10/25/2023 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/26/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/26/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/26/2023 | Corrections Issued | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 10/26/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/1/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/1/2023 | Conditional Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 11/9/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | JOHN HAYES |
| Shower Pan | 11/20/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/6/2023 | Approved | JOHN HAYES |
| Gas Test | 1/16/2024 | Approved | JOHN HAYES |
| Sewer | 1/16/2024 | Approved | JOHN HAYES |
| Underground Mechanical | 1/16/2024 | Approved | JOHN HAYES |
| Verify Rec and Parks Fee Memo | 1/16/2024 | Approved | JOHN HAYES |
| Underground Mechanical | 2/29/2024 | Partial Approval | JOHN HAYES |
| Gas Test | 5/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 6/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 6/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 6/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 6/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 6/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 6/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 6/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 6/10/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 6/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 6/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 6/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 6/13/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 6/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 6/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |