239-239 1/2 E 99TH ST 90003

Certificate Information: 239-239 1/2 E 99TH ST 90003

Application / Permit
22010-30000-04766
Plan Check / Job No.
B22WL03626
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 2 story duplex in front
Permit Issued
Issued on 9/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2022 APPLICANT
Assigned to Plan Check Engineer 10/14/2022 YASHAR EMAMI
Corrections Issued 10/17/2022 YASHAR EMAMI
Quality Review Completed 10/22/2022 KAVIAN REFAHI
Building Plans Picked Up 10/24/2022 APPLICANT
Applicant returned to address corrections 1/26/2023 YASHAR EMAMI
Applicant returned to address corrections 7/12/2023 YASHAR EMAMI
Plan Check Approved 8/29/2023 YASHAR EMAMI
Issued 9/8/2023 APPLICANT
CofO in Progress 10/10/2024 BARRY HACHE
CofO Issued 10/25/2024 ANSON MAGLASANG
Permit Finaled 10/25/2024 ANSON MAGLASANG

Permit Application Clearance Information

SB8 RUD Cleared 10/18/2022 YASHAR EMAMI
Address approval Cleared 10/20/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/25/2022 CELINA MORENO
Hydrant and Access approval Cleared 11/22/2022 MATTHEW CRAIG
Low Impact Development Cleared 11/22/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 1/12/2023 CELINA MORENO
Sewer availability Cleared 1/20/2023 CELINA MORENO

Contact Information

Architect , ; Lic. No.: C35150       ,
Contractor Moreno Chris; Lic. No.: 973501-B 1158 W 126TH STREET      LOS ANGELES, CA 90044
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/8/2024 Approved JOHN KLARIN
Underground Mechanical 1/31/2024 Partial Approval JOHN KLARIN
Wood Frame 1/31/2024 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Partial Approval JOHN KLARIN
Insulation 2/2/2024 Partial Approval JOHN KLARIN
Underground Mechanical 2/2/2024 Partial Approval JOHN KLARIN
Wood Frame 2/2/2024 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Approved BEN MOLSTAD
PLUMBING-Rough 5/9/2024 Approved BEN MOLSTAD
ELECTRICAL-Rough 5/10/2024 Approved JAMES CHAVEZ
HVAC-Rough 5/13/2024 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 5/15/2024 Approved JAMES CHAVEZ
Green Building Rough 5/15/2024 Approved JAMES CHAVEZ
Verify Sprinkler Sign Off 5/15/2024 Approved JAMES CHAVEZ
Insulation 5/20/2024 Approved BEN MOLSTAD
Drywall Nailing 6/4/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 6/4/2024 Partial Approval BEN MOLSTAD
Drywall Nailing 6/5/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 6/5/2024 Approved BEN MOLSTAD
Sewer 6/27/2024 Approved BEN MOLSTAD
Underground Mechanical 6/27/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 9/24/2024 Not Ready for Inspection BARRY HACHE
Final 9/24/2024 Not Ready for Inspection BARRY HACHE
Gas Test 9/24/2024 Approved BARRY HACHE
Green Building Final 9/24/2024 Approved BARRY HACHE
HVAC-Final 9/24/2024 Approved BARRY HACHE
PLUMBING-Final 9/24/2024 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Approved BARRY HACHE
Service/Power Release 9/24/2024 Not Ready for Inspection BARRY HACHE
Smoke Detectors 9/24/2024 Corrections Issued BARRY HACHE
ELECTRICAL-Final 10/1/2024 Approved BARRY HACHE
Final 10/1/2024 Corrections Issued BARRY HACHE
PLUMBING-Final 10/1/2024 Approved BARRY HACHE
Service/Power Release 10/1/2024 Not Ready for Inspection BARRY HACHE
Smoke Detectors 10/1/2024 Approved BARRY HACHE
ELECTRICAL-Final 10/9/2024 Approved BARRY HACHE
Final 10/9/2024 Corrections Issued BARRY HACHE
Service/Power Release 10/9/2024 Not Ready for Inspection BARRY HACHE
Final 10/10/2024 OK to Issue CofO BARRY HACHE
Service/Power Release 10/10/2024 Approved BARRY HACHE
Service/Power Release 10/17/2024 Approved ANSON MAGLASANG