4069 S MICHAEL AVE 90066
Certificate Information: 4069 S MICHAEL AVE 90066
- Application / Permit
- 22010-30000-04689
- Plan Check / Job No.
- B22WL03565
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD W/ ATT GARAGE
- Permit Issued
- Issued on 12/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | KAVIAN REFAHI |
| Corrections Issued | 10/2/2022 | KAVIAN REFAHI |
| Quality Review Completed | 10/5/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/6/2022 | APPLICANT |
| Plan Check Approved | 12/2/2022 | KAVIAN REFAHI |
| Issued | 12/2/2022 | APPLICANT |
| CofO in Progress | 12/7/2023 | RICHARD STEINBACH |
| Permit Finaled | 12/7/2023 | DANIEL ORRANTE |
| CofO Issued | 12/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2022 | CATHERINE ADROVER |
| Permit | Cleared | 10/13/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 10/19/2022 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 10/21/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 11/1/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/7/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 11/8/2022 | PEDRO AYALA |
| SB8 RUD | Cleared | 11/9/2022 | RICHARD TRUONG |
| Hydrant and Access approval | Cleared | 11/12/2022 | GILBERT URREA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/8/2023 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 3/8/2023 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/20/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/20/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 3/20/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 4/28/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/2/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 5/4/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/9/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 5/9/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/19/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 5/19/2023 | Corrections Issued | HERBERT GIRON |
| Verify Sprinkler Sign Off | 5/19/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 5/26/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/26/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/31/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/1/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/2/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/12/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/28/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/29/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 9/29/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 9/29/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 10/4/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/4/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 10/16/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/18/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 11/29/2023 | Approved | MICHAEL PELHAM |
| Final | 12/5/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Final | 12/5/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | JESUS RODRIGUEZ |