2204 1/4 S CARMONA AVE 90016
Certificate Information: 2204 1/4 S CARMONA AVE 90016
- Application / Permit
- 22010-30000-04645
- Plan Check / Job No.
- B22WL03529
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story ADU (1-bedroom ; 1-bathroom) (346 sf) at rear of the lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Issued on 7/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | REZA HAGHIGHAT |
| Corrections Issued | 9/25/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 9/30/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/13/2022 | APPLICANT |
| Plan Check Approved | 3/15/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 3/15/2023 | REZA HAGHIGHAT |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 6/12/2024 | ARTHUR NEGRETE |
| Permit Finaled | 7/30/2024 | DEROLD HAUFF |
| CofO Issued | 7/30/2024 | DEROLD HAUFF |
| Permit Finaled | 7/30/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/3/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2022 | CELINA MORENO |
| SB8 RUD | Cleared | 10/19/2022 | NICHOLAS KAWAZOE |
| Hydrant and Access approval | Cleared | 12/8/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 12/11/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/26/2023 | WALLIE JONG |
| Sewer availability | Cleared | 1/26/2023 | WALLIE JONG |
| Construction near power lines | Cleared | 3/3/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Onward Builders Llc; Lic. No.: 1084275-B | 750 N SAN VICENTE BLVD STE 800 WEST HOLLYWOOD, CA 90069 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
| Geologist | , ; Lic. No.: GEO2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 5/15/2023 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/19/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 5/19/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/26/2023 | Approved | JOSE AVILA |
| Deputy Steel/Welding | 6/1/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Deputy Steel/Welding | 6/20/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Not Ready for Inspection | JOSE AVILA |
| Wood Frame | 8/14/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Partial Inspection | RONNIE MINDANAO |
| PLUMBING-Final | 9/13/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 9/18/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 9/20/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 9/22/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/22/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 9/26/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Approved | JOSE AVILA |
| Shower Pan | 10/4/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 10/4/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/6/2023 | Approved | JOSE AVILA |
| Shower Pan | 10/6/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/12/2023 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | JOSE AVILA |
| Green Building Rough | 10/23/2023 | Approved | JOSE AVILA |
| Insulation | 10/23/2023 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 10/31/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/14/2024 | Approved | ARTHUR NEGRETE |
| Final | 5/14/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Gas Test | 5/14/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 5/14/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 5/14/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/14/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 5/14/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 5/14/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Gas Test | 5/15/2024 | Approved | ARTHUR NEGRETE |
| Grading Pre-Inspection | 5/15/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/15/2024 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 5/15/2024 | Approved | ARTHUR NEGRETE |
| Final | 6/3/2024 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 6/3/2024 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 6/7/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 6/7/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 6/7/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 6/11/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 6/11/2024 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 6/11/2024 | Approved | ARTHUR NEGRETE |