1428 W 51ST PL 90062

Certificate Information: 1428 W 51ST PL 90062

Application / Permit
22010-30000-04628
Plan Check / Job No.
B22WL03512
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ACCESSORY DWELLING UNIT
Permit Issued
Issued on 3/31/2023
Issuing Office
Valley
Current Status
Issued on 3/31/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/19/2022 APPLICANT
Assigned to Plan Check Engineer 9/21/2022 RICHARD GARCIA
Corrections Issued 9/22/2022 RICHARD GARCIA
Building Plans Picked Up 9/28/2022 APPLICANT
Applicant returned to address corrections 11/4/2022 RICHARD GARCIA
Applicant returned to address corrections 11/28/2022 JASON JANGADA
Applicant returned to address corrections 2/28/2023 JOHNPAUL ISIP
Applicant returned to address corrections 3/14/2023 RICHARD GARCIA
Plan Check Approved 3/23/2023 JOHNPAUL ISIP
Issued 3/31/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/1/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/4/2022 STEVE MELGAR
Sewer availability Cleared 10/4/2022 STEVE MELGAR
Low Impact Development Cleared 10/20/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/20/2022 TREVOR QUAN
Community Plan Implem. Overlay Cleared 12/1/2022 TREVOR QUAN
Community Plan Implem. Overlay Cleared 12/5/2022 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 2/25/2023 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 3/9/2023 RAFAEL FONTES

Contact Information

Contractor 123 Restoration Specialists Inc; Lic. No.: 1010734-B 9556 COZYCROFT AVE      CHATSWORTH, CA 91311
Engineer Alferez,, Vicente Narvaez; Lic. No.: C53875 460 E CARSON PLAZA DR STE 212      CARSON, CA 90746

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/22/2023 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 6/7/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 6/12/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 8/11/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 8/11/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 9/20/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/3/2023 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Corrections Issued RONNIE MINDANAO
Green Building Rough 10/3/2023 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 10/3/2023 Approved RONNIE MINDANAO
Verify Sprinkler Sign Off 10/3/2023 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 10/4/2023 Partial Inspection RONNIE MINDANAO
Wood Frame 10/4/2023 Approved RONNIE MINDANAO
Green Building Rough 10/18/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/18/2023 Partial Approval JUSTIN HAWLEY
Insulation 11/2/2023 Corrections Issued CRAIG DAVIS
Insulation 11/16/2023 Partial Inspection CRAIG DAVIS
Drywall Nailing 11/27/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 11/27/2023 Approved BRENDAN MORELLI
Shower Pan 11/27/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 1/16/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 1/16/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 1/16/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/16/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 1/16/2024 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 1/16/2024 Approved ALIZAH MAYAGOITIA
Final 2/12/2024 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/12/2024 Approved ENRIQUE MIRELES
Green Building Final 2/12/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 2/12/2024 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 2/12/2024 Approved ENRIQUE MIRELES
Final 2/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 2/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 3/28/2024 Corrections Issued CRAIG DAVIS
Service/Power Release 3/28/2024 Not Ready for Inspection CRAIG DAVIS
Final 4/8/2024 Partial Inspection CRAIG DAVIS
Service/Power Release 4/8/2024 Corrections Issued CRAIG DAVIS
Final 4/19/2024 Partial Inspection CRAIG DAVIS
Service/Power Release 4/19/2024 Partial Inspection CRAIG DAVIS
Final 5/23/2024 Corrections Issued CRAIG DAVIS
Service/Power Release 5/23/2024 Corrections Issued CRAIG DAVIS