1572 S CARDIFF AVE 90035
Certificate Information: 1572 S CARDIFF AVE 90035
- Application / Permit
- 22010-30000-04502
- Plan Check / Job No.
- B22WL03440
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition and major remodel to existing SFD. 2'of existing wall and foundation to remain *** 1 of 2 ***
- Permit Issued
- Issued on 8/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | KAVIAN REFAHI |
| Corrections Issued | 9/18/2022 | KAVIAN REFAHI |
| Quality Review Completed | 9/21/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 12/1/2022 | KAVIAN REFAHI |
| Plan Check Approved | 12/12/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 1/6/2023 | APPLICANT |
| Issued | 8/2/2023 | APPLICANT |
| CofO in Progress | 1/20/2026 | ASHLEY THOMPSON |
| Permit Finaled | 1/21/2026 | RICHARD STEINBACH |
| CofO Issued | 1/21/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/21/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | DINAH GARIN |
| Sewer availability | Cleared | 10/25/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 11/4/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 11/8/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 12/12/2022 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 12/12/2022 | KAVIAN REFAHI |
Contact Information
| Contractor | Harari Construction Inc; Lic. No.: 1017539-B | 9719 OAKMORE ROAD LOS ANGELES, CA 90035 |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/11/2023 | Partial Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/14/2023 | Corrections Issued | MICHAEL PELHAM |
| METHANE-Subgrade | 10/19/2023 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 11/3/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| METHANE-Barrier | 11/3/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 11/6/2023 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 11/6/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 11/6/2023 | Approved | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 11/8/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 11/16/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 11/17/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/26/2024 | Approved | SEAN HAUPT |
| Gas Test | 6/26/2024 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 6/26/2024 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 6/26/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Partial Approval | ASHLEY THOMPSON |
| HVAC-Rough | 9/20/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/20/2024 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 11/15/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 11/15/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 11/15/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 11/15/2024 | Approved | ASHLEY THOMPSON |
| Wood Frame | 11/15/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/6/2025 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 1/6/2025 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 1/6/2025 | Partial Approval | KENNETH NAGLE |
| METHANE-Rough | 1/6/2025 | Corrections Issued | KENNETH NAGLE |
| BUILDING-Rough-Frame | 1/14/2025 | Partial Approval | JESUS RODRIGUEZ |
| Insulation | 1/14/2025 | Approved | JESUS RODRIGUEZ |
| METHANE-Rough | 1/14/2025 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 1/29/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 2/10/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/19/2025 | Approved | MEL KHACHATOURIAN |
| Verify Rec and Parks Fee Memo | 7/28/2025 | Partial Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/23/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 10/30/2025 | Conditional Approval | ASHLEY THOMPSON |
| Service/Power Release | 10/30/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 11/21/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 12/2/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/5/2025 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 12/5/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 12/8/2025 | Approved | EVAN COOPER |
| HVAC-Final | 12/19/2025 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/26/2025 | Approved | ASHLEY THOMPSON |
| Final | 12/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 12/26/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 12/26/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 12/26/2025 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 12/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/9/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Final | 1/12/2026 | Corrections Issued | ASHLEY THOMPSON |
| Final | 1/15/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 1/15/2026 | Approved | ASHLEY THOMPSON |