3323 S VETERAN AVE 90034
Certificate Information: 3323 S VETERAN AVE 90034
- Application / Permit
- 22010-30000-04483
- Plan Check / Job No.
- B22WL03416
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story accessory structure with garage (223 sf) and carport (273 sf) at 1st floor and ADU (510 sf) at 2nd floor at rear of the lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 10/19/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | REZA HAGHIGHAT |
| Corrections Issued | 10/3/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 10/11/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 11/18/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 8/2/2023 | REZA HAGHIGHAT |
| Issued | 10/19/2023 | APPLICANT |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/20/2023 | KIRK LINKLATER |
| Construction near power lines | Cleared | 5/2/2023 | RIDWAN HARDY |
| Address approval | Cleared | 5/3/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2023 | JASON NG |
| Sewer availability | Cleared | 5/4/2023 | JASON NG |
| Low Impact Development | Cleared | 5/17/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/18/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 6/12/2023 | PEDRO AYALA |
| GPI Written Notices | Cleared | 8/2/2023 | REZA HAGHIGHAT |
| Hold | Cleared | 11/21/2023 | CARMEN MERAZ |
Contact Information
| Contractor | Re3 Restoration Llc; Lic. No.: 1037548-B | 1137 S BRANNICK AVENUE LOS ANGELES, CA 90023 |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 10/27/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/31/2023 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 11/28/2023 | Approved | JESUS PINEDA |
| Gas Test | 11/28/2023 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 12/1/2023 | Approved | JESUS PINEDA |
| Underground Mechanical | 12/1/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 1/26/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 1/26/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 2/22/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 2/22/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 2/22/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 2/29/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 2/29/2024 | Approved | JESUS PINEDA |
| Insulation | 2/29/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/29/2024 | Partial Approval | JESUS PINEDA |
| Verify Sprinkler Sign Off | 2/29/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/14/2024 | No Access for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/18/2024 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 4/16/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 7/12/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 7/12/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 7/12/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 8/2/2024 | Approved | JESUS PINEDA |
| Final | 8/2/2024 | Corrections Issued | JESUS PINEDA |
| Gas Test | 8/2/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 8/2/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/2/2024 | Approved | JESUS PINEDA |
| Final | 9/5/2024 | Partial Approval | DANIEL VERA |
| Green Building Final | 9/5/2024 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | DANIEL VERA |
| Service/Power Release | 9/5/2024 | Approved | DANIEL VERA |
| Smoke Detectors | 9/5/2024 | Approved | DANIEL VERA |
| Structural Steel Frame | 9/5/2024 | Approved | DANIEL VERA |
| Final | 9/9/2024 | Corrections Issued | DANIEL VERA |
| Final | 9/13/2024 | Corrections Issued | MICHAEL PELHAM |
| Final | 10/19/2024 | Corrections Issued | MICHAEL PELHAM |
| Final | 11/8/2024 | Conditional Approval | MICHAEL PELHAM |