3706 S BARRY AVE 90066
Certificate Information: 3706 S BARRY AVE 90066
- Application / Permit
- 22010-30000-04437
- Plan Check / Job No.
- B22WL03386
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story House Addition, remove entire S.F.D. but 2' of fdn. & wall *** 1 of 2 ***
- Permit Issued
- Issued on 10/19/2022
- Issuing Office
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | KAVIAN REFAHI |
| Corrections Issued | 9/11/2022 | KAVIAN REFAHI |
| Quality Review Completed | 9/16/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 10/17/2022 | KAVIAN REFAHI |
| Issued | 10/19/2022 | APPLICANT |
| Building Plans Picked Up | 10/25/2022 | APPLICANT |
| CofO in Progress | 5/23/2024 | JESUS PINEDA |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
| CofO Issued | 5/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 9/13/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/15/2022 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 9/20/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/22/2022 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 10/4/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 10/17/2022 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 10/17/2022 | KAVIAN REFAHI |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Pre-Inspection | 10/28/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/26/2023 | Corrections Issued | DAVID FEILER |
| Sewer | 1/26/2023 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 2/7/2023 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 2/7/2023 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 2/16/2023 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 3/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 3/6/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/26/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 4/26/2023 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 4/26/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 6/27/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Approved | JESUS PINEDA |
| Special/Order Compliance | 8/3/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 8/14/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 8/16/2023 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 8/18/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 8/18/2023 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 8/21/2023 | No Access for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 8/28/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 8/28/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 9/5/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 9/5/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/5/2023 | Partial Approval | JESUS PINEDA |
| Shower Pan | 9/14/2023 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 9/14/2023 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Rough | 9/21/2023 | Approved | JESUS PINEDA |
| Shower Pan | 9/21/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/28/2023 | Corrections Issued | RICHARD STEINBACH |
| Green Building Rough | 9/28/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 9/28/2023 | Corrections Issued | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 9/28/2023 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | RICHARD STEINBACH |
| Insulation | 10/4/2023 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 10/4/2023 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 10/17/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 10/17/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 2/21/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 2/29/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 2/29/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 3/13/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 4/3/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 4/3/2024 | Corrections Issued | BOBBY KEY |
| Final | 4/10/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 4/10/2024 | Approved | JESUS PINEDA |
| Green Building Final | 4/10/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 4/10/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 4/10/2024 | Approved | JESUS PINEDA |
| Final | 4/18/2024 | Not Ready for Inspection | JESUS PINEDA |
| Gas Test | 4/18/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 4/18/2024 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Not Ready | JESUS PINEDA |
| Final | 5/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 5/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 5/21/2024 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Not Ready | JESUS PINEDA |
| Service/Power Release | 5/21/2024 | Approved | JESUS PINEDA |
| Final | 5/23/2024 | OK to Issue CofO | JESUS PINEDA |
| PLUMBING-Final | 5/23/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | JESUS PINEDA |