1850 S BENECIA AVE 90025
Certificate Information: 1850 S BENECIA AVE 90025
- Application / Permit
- 22010-30000-04436
- Plan Check / Job No.
- B22WL03381
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story S.F.D. (5,281 sf) w/ att. 2-car garage (410 sf)
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | REZA HAGHIGHAT |
| Corrections Issued | 9/19/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 9/22/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/12/2022 | APPLICANT |
| Plan Check Approved | 7/27/2023 | REZA HAGHIGHAT |
| Issued | 8/10/2023 | APPLICANT |
| CofO in Progress | 4/5/2025 | DANIEL VERA |
| CofO Issued | 4/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/8/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 6/23/2023 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 6/28/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 7/7/2023 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 7/16/2023 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 7/27/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 7/27/2023 | REZA HAGHIGHAT |
Contact Information
| Architect | Dy,, Christine; Lic. No.: C37594 | 11423 OHIO AVENUE #16 LOS ANGELES, CA 90025 |
| Contractor | Eskan Builders Corp; Lic. No.: 1023638-B | 19451 SHERMAN WAY UNIT 506 RESEDA, CA 91335 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 17514 VENTURA BLVD. SUITE 206 ENCINO, CA 91346 |
| Geologist | , ; Lic. No.: GEO2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2023 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Inspection | 11/7/2023 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 11/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 11/20/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/21/2023 | Partial Approval | STEPHANIE SWANSON |
| Grounding or Bonding | 11/21/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 11/21/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 11/21/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/21/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/7/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Barrier | 12/7/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 12/7/2023 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 12/19/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Partial Approval | STEPHANIE SWANSON |
| Wood Frame | 12/19/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 1/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Special/Order Compliance | 1/3/2024 | Partial Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 2/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/16/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 3/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 3/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 3/8/2024 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 3/11/2024 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 3/19/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 3/22/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 3/26/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/26/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/28/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/28/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 3/28/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 3/28/2024 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 3/28/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 4/3/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/3/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 4/5/2024 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/18/2024 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 4/18/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 4/19/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/22/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 5/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 5/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Smoke Detectors | 10/8/2024 | Approved | STEPHANIE SWANSON |
| Gas Test | 10/9/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Gas Test | 10/10/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Gas Test | 10/15/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/21/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Final | 11/7/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Drywall Nailing | 11/14/2024 | Approved | STEPHANIE SWANSON |
| Final | 11/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 11/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 11/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 12/2/2024 | Approved | STEPHANIE SWANSON |
| Final | 12/13/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 12/13/2024 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 12/13/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Final | 12/19/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 1/3/2025 | Approved | STEPHANIE SWANSON |
| Final | 2/20/2025 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 2/20/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Final | 4/4/2025 | OK to Issue CofO | DANIEL VERA |
| Service/Power Release | 4/4/2025 | Approved | DANIEL VERA |