2136 S GREENFIELD AVE 90025

Certificate Information: 2136 S GREENFIELD AVE 90025

Application / Permit
22010-30000-04354
Plan Check / Job No.
B21WL04048
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage Conversion to ADU and Addition per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c),(d),(g)
Permit Issued
Issued on 2/6/2023
Issuing Office
Current Status
CofO Issued on 8/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 DAVID CASTILLO
Corrections Issued 10/19/2021 DAVID CASTILLO
Quality Review Completed 10/27/2021 TARIK SAOUD
Applicant returned to address corrections 7/1/2022 DAVID CASTILLO
Applicant returned to address corrections 8/30/2022 DAVID CASTILLO
Applicant returned to address corrections 9/8/2022 DAVID CASTILLO
Building Plans Picked Up 9/13/2022 APPLICANT
Applicant returned to address corrections 12/19/2022 DAVID CASTILLO
Applicant returned to address corrections 1/6/2023 DAVID CASTILLO
Applicant returned to address corrections 1/18/2023 DAVID CASTILLO
Plan Check Approved 2/3/2023 DAVID CASTILLO
Issued 2/6/2023 APPLICANT
CofO in Progress 8/5/2024 KIRK SANDERS
Permit Finaled 8/8/2024 DANIEL ORRANTE
CofO Issued 8/8/2024 DANIEL ORRANTE
Permit Finaled 8/8/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/21/2022 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 9/21/2022 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 9/21/2022 AHMED AMARRAGY
Sewer availability Cleared 9/21/2022 AHMED AMARRAGY
Grading Pre-Inspection Cleared 9/29/2022 KIRK LINKLATER
Specific Plan Cleared 10/20/2022 ROBERT SANCHEZ
Construction within easement Cleared 11/17/2022 RIDWAN HARDY
Low Impact Development Cleared 12/8/2022 AMMAR ELTAWIL

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2023 Corrections Issued JESUS PINEDA
HVAC-Rough 9/19/2023 Not Ready for Inspection CARLOS MATAMOROS
Special/Order Compliance 9/25/2023 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 9/29/2023 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 10/5/2023 Partial Approval CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 10/20/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval MICHAEL PELHAM
ELECTRICAL-Rough 1/3/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/22/2024 No Access for Inspection BEN MOLSTAD
Green Building Rough 1/22/2024 No Access for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 1/22/2024 No Access for Inspection BEN MOLSTAD
Underground Mechanical 2/28/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 6/7/2024 Corrections Issued KIRK SANDERS
HVAC-Final 6/7/2024 Approved KIRK SANDERS
PLUMBING-Final 6/7/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 6/21/2024 Corrections Issued KIRK SANDERS
PLUMBING-Final 6/21/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 7/3/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/8/2024 Approved KIRK SANDERS
Drywall Nailing 7/8/2024 Approved KIRK SANDERS
Final 7/8/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 7/8/2024 Approved KIRK SANDERS
Green Building Final 7/8/2024 Approved KIRK SANDERS
Green Building Rough 7/8/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved KIRK SANDERS
Smoke Detectors 7/8/2024 Approved KIRK SANDERS
Verify Sprinkler Sign Off 7/8/2024 Approved KIRK SANDERS
Final 8/2/2024 OK to Issue CofO KIRK SANDERS
Service/Power Release 8/2/2024 Approved KIRK SANDERS