966 N SANBORN AVE #C - #D 90029

Certificate Information: 966 N SANBORN AVE #C - #D 90029

Application / Permit
22010-30000-04297
Plan Check / Job No.
B22WL03292
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story SFD (1,696 sf) (4 bedrooms ; 4 1/2 bathrooms) (Unit C) w./ att. ADU (1,579 sf) (3 bedrooms ; 3 1/2 bathrooms) (Unit D) per LAMC 12.22 A.33 (c) - (d) and roof deck at rear of the lot ; (Building 2)
Permit Issued
Issued on 2/27/2023
Issuing Office
Current Status
CofO Issued on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 REZA HAGHIGHAT
Corrections Issued 9/11/2022 REZA HAGHIGHAT
Re-Submittal Required 9/16/2022 CHIHARU SUZUKI
Re-Submitted 10/5/2022 REZA HAGHIGHAT
Corrections Issued 2 10/5/2022 REZA HAGHIGHAT
Submitted for Second Quality Review 10/15/2022 KAVIAN REFAHI
Quality Review Completed 10/15/2022 KAVIAN REFAHI
Building Plans Picked Up 10/17/2022 APPLICANT
Plan Check Approved 2/13/2023 REZA HAGHIGHAT
Issued 2/27/2023 APPLICANT
CofO in Progress 11/13/2024 FREDDIE RIVERA
No Progress 11/13/2024 FREDDIE RIVERA
CofO in Progress 11/13/2024 FREDDIE RIVERA
Permit Finaled 11/21/2024 DEROLD HAUFF
CofO Issued 11/21/2024 DEROLD HAUFF
Permit Finaled 11/21/2024 DEROLD HAUFF

Permit Application Clearance Information

SB8 RUD Cleared 10/19/2022 LOUIE MILLER
Address approval Cleared 10/31/2022 WALLIE JONG
BHO/Hillside ordinance Cleared 10/31/2022 WALLIE JONG
BHO/Hillside ordinance Cleared 11/1/2022 WALLIE JONG
BHO/Hillside ordinance Cleared 11/1/2022 WALLIE JONG
BHO/Hillside ordinance Cleared 11/1/2022 WALLIE JONG
BHO/Hillside ordinance Cleared 11/1/2022 WALLIE JONG
"D" conditions Cleared 11/3/2022 ANACANY HURTADO
"Q" conditions Cleared 11/3/2022 ANACANY HURTADO
Frnt yard landscape/Water mgmt Cleared 11/7/2022 ANACANY HURTADO
Hydrant and Access approval Cleared 11/10/2022 RUEL COLE
Construction near power lines Cleared 2/3/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/10/2023 WALLIE JONG
Low Impact Development Cleared 2/10/2023 MITESH PATEL
GPI Written Notices Cleared 2/13/2023 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 2/13/2023 REZA HAGHIGHAT
Roof/Waste drainage to street Cleared 2/13/2023 TREVOR QUAN
Sewer availability Cleared 2/13/2023 TREVOR QUAN

Contact Information

Contractor Onward Builders Llc; Lic. No.: 1084275-B 750 N SAN VICENTE BLVD STE 800      WEST HOLLYWOOD, CA 90069
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/22/2023 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 5/22/2023 Partial Approval FREDDIE RIVERA
Deputy Reinf. Concrete 5/30/2023 Approved FREDDIE RIVERA
Footing/Foundation/Slab 5/30/2023 Approved FREDDIE RIVERA
Deputy Steel/Welding 6/1/2023 Conditional Approval FREDDIE RIVERA
Deputy Steel/Welding 6/20/2023 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 10/10/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 10/10/2023 Corrections Issued FREDDIE RIVERA
HVAC-Rough 10/13/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/25/2023 Partial Inspection FREDDIE RIVERA
Green Building Rough 10/25/2023 Partial Inspection FREDDIE RIVERA
Shower Pan 10/25/2023 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 10/25/2023 Approved FREDDIE RIVERA
Wood Frame 10/25/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 10/27/2023 Corrections Issued FREDDIE RIVERA
Green Building Rough 10/27/2023 Approved FREDDIE RIVERA
MERV13>=Rough 10/27/2023 Partial Inspection FREDDIE RIVERA
Shower Pan 10/27/2023 Approved FREDDIE RIVERA
Wood Frame 10/27/2023 Partial Inspection FREDDIE RIVERA
Insulation 10/30/2023 Corrections Issued FREDDIE RIVERA
Insulation 11/2/2023 Approved FREDDIE RIVERA
Drywall Nailing 11/14/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/14/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 No Access for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/17/2023 No Access for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/1/2024 Approved FREDDIE RIVERA
Gas Test 10/1/2024 Partial Inspection FREDDIE RIVERA
HVAC-Final 10/1/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 10/1/2024 Approved FREDDIE RIVERA
Service/Power Release 10/1/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 10/25/2024 Partial Inspection FREDDIE RIVERA
Final 10/25/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 10/25/2024 Approved FREDDIE RIVERA
HVAC-Final 10/25/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Approved FREDDIE RIVERA
Service/Power Release 10/25/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 10/25/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/29/2024 Approved FREDDIE RIVERA
Final 10/29/2024 OK to Issue CofO FREDDIE RIVERA
Gas Test 10/29/2024 Approved FREDDIE RIVERA
Service/Power Release 10/29/2024 Approved FREDDIE RIVERA
Special/Order Compliance 11/13/2024 Corrections Issued FREDDIE RIVERA