1246 E MORNINGSIDE WAY 90291
Certificate Information: 1246 E MORNINGSIDE WAY 90291
- Application / Permit
- 22010-30000-04221
- Plan Check / Job No.
- B22WL03219
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition and major remodel to existing SFD ** 1 of 2 **
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | KAVIAN REFAHI |
| Corrections Issued | 9/6/2022 | KAVIAN REFAHI |
| Quality Review Completed | 9/15/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 12/4/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/13/2022 | KAVIAN REFAHI |
| Plan Check Approved | 1/13/2023 | KAVIAN REFAHI |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 4/1/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 4/3/2025 | RICHARD STEINBACH |
| CofO Issued | 4/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/21/2022 | LONDY ALVARADO |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | DINAH GARIN |
| Sewer availability | Cleared | 10/3/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 10/27/2022 | KURT CORRAL |
| Specific Plan | Cleared | 11/1/2022 | ROBERT SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/23/2022 | JENSON LEE |
| GPI Written Notices | Cleared | 12/13/2022 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 12/13/2022 | KAVIAN REFAHI |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/30/2023 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 12/4/2023 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 12/8/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 12/8/2023 | Approved | HERBERT GIRON |
| Sewer | 12/14/2023 | Approved | HERBERT GIRON |
| Underground Mechanical | 12/14/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 2/13/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Partial Approval | HERBERT GIRON |
| Gas Test | 2/23/2024 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 2/23/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/26/2024 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 2/28/2024 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 3/21/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 4/11/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 5/9/2024 | Approved | HERBERT GIRON |
| Shower Pan | 5/9/2024 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 5/9/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/22/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 7/22/2024 | Approved | HERBERT GIRON |
| Shower Pan | 7/22/2024 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Wood Construction | 7/23/2024 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/30/2024 | Approved | HERBERT GIRON |
| Shower Pan | 7/30/2024 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 8/1/2024 | Approved | HERBERT GIRON |
| Shower Pan | 8/1/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/14/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/14/2024 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 8/26/2024 | Approved | HERBERT GIRON |
| Gas Test | 2/20/2025 | Approved | JAYLIN GRAVITTE |
| PLUMBING-Final | 3/7/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/10/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 3/10/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 3/12/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 3/12/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 3/20/2025 | Approved | JESUS RODRIGUEZ |
| Final | 3/26/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 3/26/2025 | Approved | JESUS RODRIGUEZ |
| Final | 3/28/2025 | OK to Issue CofO | TEMISTOCLES CAAL |