1354 N LACHMAN LANE 90272
Certificate Information: 1354 N LACHMAN LANE 90272
- Application / Permit
- 22010-30000-04139
- Plan Check / Job No.
- B22WL03177
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 1-story S.F.D. with attahed 3-car garage over partial basement Rec-room *** 1 of 2 ***
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | KAVIAN REFAHI |
| Corrections Issued | 9/18/2022 | KAVIAN REFAHI |
| Quality Review Completed | 9/22/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 9/23/2022 | APPLICANT |
| Applicant returned to address corrections | 12/19/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/20/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/13/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/9/2024 | KAVIAN REFAHI |
| Plan Check Approved | 2/28/2024 | KAVIAN REFAHI |
| Issued | 2/29/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/30/2022 | DINAH GARIN |
| Trees in Parkway | Cleared | 10/5/2022 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2022 | DINAH GARIN |
| Permit | Cleared | 10/6/2022 | DINAH GARIN |
| Sewer availability | Cleared | 10/6/2022 | DINAH GARIN |
| GPI Written Notices | Cleared | 1/13/2023 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 1/13/2023 | KAVIAN REFAHI |
| Hydrant and Access approval | Cleared | 1/13/2023 | LAVEON RIDER |
| Miscellaneous | Cleared | 1/17/2023 | LOUIS ORTEGA |
| ZA Case | Cleared | 1/17/2023 | LOUIS ORTEGA |
| Coastal Zone | Cleared | 11/29/2023 | RYAN LY |
| Mello Bill | Cleared | 11/29/2023 | RYAN LY |
| ZI | Cleared | 11/29/2023 | RYAN LY |
| Low Impact Development | Cleared | 2/1/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/8/2024 | HISASHI KOBAYAKAWA |
| Excavation more than 5-ft deep | Cleared | 2/9/2024 | CALOSHA APPROVED |
Contact Information
| Architect | Knowlton,, Ryan T; Lic. No.: C27257 | 1601 N. SEPULVEDA BLVD #722 MANHATTAN BEACH, CA 90266 |
| Contractor | Reis Ey Inc; Lic. No.: 1067133-B | 286 MADISON AVE FLOOR 21 NEW YORK, NY 10017 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
| Landscape Architect | Zucker,, Scott Alan; Lic. No.: LA2729 | 26691 PARISO DRIVE MISSION VIEJO, CA 92691 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/22/2024 | Approved | EVAN COOPER |
| PLUMBING-Rough | 8/26/2024 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 8/26/2024 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 8/28/2024 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/29/2024 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 9/13/2024 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/24/2024 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 10/2/2024 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 10/17/2024 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 1/3/2025 | Partial Approval | EVAN COOPER |
| Sewer | 1/3/2025 | Approved | EVAN COOPER |
| Underground Mechanical | 1/3/2025 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 1/6/2025 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 4/25/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 4/25/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 5/20/2025 | Partial Approval | BOBBY KEY |
| Deputy Wood Construction | 6/9/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Partial Approval | TEMISTOCLES CAAL |
| Structural Steel Frame | 6/23/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 7/3/2025 | Conditional Approval | BOBBY KEY |
| Deputy Steel/Welding | 7/7/2025 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 7/11/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Structural Steel Frame | 7/11/2025 | Partial Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 7/11/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 7/14/2025 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Partial Approval | BOBBY KEY |
| Deputy Steel/Welding | 8/14/2025 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 8/20/2025 | Conditional Approval | BOBBY KEY |
| Deputy Steel/Welding | 8/28/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 8/29/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Steel/Welding | 9/4/2025 | Conditional Approval | BOBBY KEY |
| Deputy Steel/Welding | 9/5/2025 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 10/16/2025 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Partial Approval | BOBBY KEY |
| Deputy Steel/Welding | 12/5/2025 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 12/10/2025 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 12/10/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 1/2/2026 | Approved | BOBBY KEY |
| Underground Mechanical | 1/2/2026 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 1/14/2026 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/9/2026 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 5/27/2026 | Conditional Approval | DANIEL VERA |
| ELECTRICAL-Rough | 5/27/2026 | Approved | DANIEL VERA |
| Green Building Rough | 5/27/2026 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 5/27/2026 | Partial Approval | DANIEL VERA |
| Verify Sprinkler Sign Off | 5/27/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 6/8/2026 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 6/8/2026 | Approved | ARAM AVEDISIAN |
| Insulation | 6/10/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 6/16/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 7/7/2026 | Approved | ARAM AVEDISIAN |