815 N KINGSLEY DR 90029
Certificate Information: 815 N KINGSLEY DR 90029
- Application / Permit
- 22010-30000-03837
- Plan Check / Job No.
- B22WL02950
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story accessory structure with carport at 1st floor and ADU at 2nd floor (1,113 sf) per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/2/2023
- Issuing Office
- Current Status
- CofO Issued on 7/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | REZA HAGHIGHAT |
| Corrections Issued | 8/16/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 8/24/2022 | TARIK SAOUD |
| Building Plans Picked Up | 9/2/2022 | APPLICANT |
| Applicant returned to address corrections | 11/17/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 1/10/2023 | REZA HAGHIGHAT |
| Issued | 2/2/2023 | APPLICANT |
| CofO in Progress | 7/13/2023 | JEFFREY MEAD |
| No Progress | 7/19/2023 | SCOTT FINNILA |
| CofO in Progress | 7/19/2023 | DEROLD HAUFF |
| CofO Issued | 7/19/2023 | DEROLD HAUFF |
| Permit Finaled | 7/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/6/2022 | JEANETTE VONG |
| DAS Clearance | Cleared | 9/8/2022 | REZA HAGHIGHAT |
| Hydrant and Access approval | Cleared | 10/13/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 10/31/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | STEVE MELGAR |
| Green Code | Cleared | 12/14/2022 | REZA HAGHIGHAT |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 2/10/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/14/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 3/17/2023 | Conditional Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 4/11/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/11/2023 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 4/11/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 4/11/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 4/11/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/17/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/25/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 4/25/2023 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/26/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/26/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 4/26/2023 | Partial Approval | JEFFREY MEAD |
| MERV13>=Rough | 4/26/2023 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 4/26/2023 | Approved | JEFFREY MEAD |
| Insulation | 4/27/2023 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 5/1/2023 | Approved | JEFFREY MEAD |
| MERV13>=Rough | 5/1/2023 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 5/1/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 5/5/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 5/19/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 7/10/2023 | Approved | JEFFREY MEAD |
| Final | 7/10/2023 | OK to Issue CofO | JEFFREY MEAD |
| Gas Test | 7/10/2023 | Approved | JEFFREY MEAD |
| Green Building Final | 7/10/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 7/10/2023 | Approved | JEFFREY MEAD |
| MERV13>=Final | 7/10/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 7/10/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 7/10/2023 | Approved | JEFFREY MEAD |
| Smoke Detectors | 7/10/2023 | Approved | JEFFREY MEAD |