5347 1/2 W RUSSELL AVE 90027
Certificate Information: 5347 1/2 W RUSSELL AVE 90027
- Application / Permit
- 22010-30000-03813
- Plan Check / Job No.
- B22WL02938
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2 (n) side by side attached ADUs behind the garage (detached from garage) in Vermont Specific Plans per state law
- Permit Issued
- Issued on 3/24/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | YASHAR EMAMI |
| Corrections Issued | 8/12/2022 | YASHAR EMAMI |
| Quality Review Completed | 8/24/2022 | TARIK SAOUD |
| Building Plans Picked Up | 9/15/2022 | APPLICANT |
| Applicant returned to address corrections | 3/3/2023 | YASHAR EMAMI |
| Plan Check Approved | 3/23/2023 | YASHAR EMAMI |
| Issued | 3/24/2023 | APPLICANT |
| CofO in Progress | 1/17/2024 | BRIAN SULLIVAN |
| Permit Finaled | 2/22/2024 | DEROLD HAUFF |
| CofO Issued | 2/22/2024 | DEROLD HAUFF |
| Permit Finaled | 2/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/22/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 12/5/2022 | LIKYELESH ABERA |
| ZI | Cleared | 12/5/2022 | LIKYELESH ABERA |
| Address approval | Cleared | 12/6/2022 | CINDY QI |
| Tenant Habitability Plan | Cleared | 12/6/2022 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2022 | CINDY QI |
| Sewer availability | Cleared | 12/8/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 12/13/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 2/3/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/8/2023 | AHMED AMARRAGY |
| GPI Written Notices | Cleared | 3/15/2023 | YASHAR EMAMI |
| Miscellaneous | Cleared | 3/16/2023 | EDMOND LEE |
Contact Information
| Architect | Sheriff,, Garth Irving; Lic. No.: C7751 | C-O REGUS 6080 CENTER DR 6TH FLR LOS ANGELES, CA 90045 |
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/4/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/13/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 4/21/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 4/21/2023 | Off-Hour Fees Due | |
| Drywall Nailing | 4/25/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 4/25/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/25/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 4/25/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 5/1/2023 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/17/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/17/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/17/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 5/17/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/18/2023 | Approved | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 5/18/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/2/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 6/16/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/16/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/17/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/17/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 8/10/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/16/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/23/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Final | 9/28/2023 | Partial Approval | JOAQUIN GREENOUGH |
| HVAC-Final | 10/16/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 10/16/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 10/23/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 10/26/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/16/2024 | Approved | BRIAN SULLIVAN |
| Final | 1/16/2024 | OK to Issue CofO | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/16/2024 | Approved | BRIAN SULLIVAN |
| Green Building Final | 1/16/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 1/16/2024 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 1/16/2024 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 1/16/2024 | Approved | BRIAN SULLIVAN |