22535-22537 W SYLVAN ST 91367

Certificate Information: 22535-22537 W SYLVAN ST 91367

Application / Permit
22010-30000-03726
Plan Check / Job No.
B22WL02882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) attached garage into (n)ADU with addition *** 1 of 2 ***
Permit Issued
Issued on 4/19/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 FELIPE HERNANDEZ
Corrections Issued 8/25/2022 FELIPE HERNANDEZ
Quality Review Completed 9/6/2022 CHIHARU SUZUKI
Applicant returned to address corrections 10/31/2022 KAVIAN REFAHI
Applicant returned to address corrections 12/6/2022 KAVIAN REFAHI
Applicant returned to address corrections 12/15/2022 KAVIAN REFAHI
Building Plans Picked Up 1/12/2023 APPLICANT
Plan Check Approved 3/22/2023 KAVIAN REFAHI
No Progress 3/22/2023 KAVIAN REFAHI
Plan Check Approved 4/19/2023 KAVIAN REFAHI
Issued 4/19/2023 APPLICANT
CofO in Progress 4/8/2024 TROY SANDERS
No Progress 10/10/2024 TROY SANDERS
CofO in Progress 10/10/2024 TROY SANDERS
CofO Issued 1/2/2025 JOHN JANSON
Permit Finaled 1/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/19/2022 CARLOS AGUILERA
Permit Cleared 10/19/2022 CARLOS AGUILERA
Sewer availability Cleared 10/19/2022 CARLOS AGUILERA
GPI Written Notices Cleared 12/15/2022 KAVIAN REFAHI
Grading Pre-Inspection Cleared 3/7/2023 VASIL MIHALEV

Contact Information

Contractor Kbk Enterprises Inc; Lic. No.: 1093465-B 1146 BURTONWOOD AVE      THOUSAND OAKS, CA 91360
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/1/2023 Partial Approval TROY SANDERS
Footing/Foundation/Slab 5/5/2023 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 5/17/2023 Partial Approval TROY SANDERS
Green Building Rough 5/17/2023 Not Ready for Inspection TROY SANDERS
Insulation 5/26/2023 Approved HORACE FULTZ
BUILDING-Rough-Frame 6/2/2023 Partial Approval TROY SANDERS
Drywall Nailing 6/2/2023 Partial Approval TROY SANDERS
Rough-Elec/Plmb/HVAC 6/2/2023 Partial Approval TROY SANDERS
ELECTRICAL-Final 10/30/2023 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Final 11/14/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 4/8/2024 Approved TROY SANDERS
Drywall Nailing 4/8/2024 Approved TROY SANDERS
ELECTRICAL-Rough 4/8/2024 Approved TROY SANDERS
Final 4/8/2024 OK to Issue CofO TROY SANDERS
Footing/Foundation/Slab 4/8/2024 Approved TROY SANDERS
Green Building Final 4/8/2024 Approved TROY SANDERS
Green Building Rough 4/8/2024 Approved TROY SANDERS
HVAC-Rough 4/8/2024 Approved TROY SANDERS
PLUMBING-Rough 4/8/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 4/8/2024 Approved TROY SANDERS
Special/Order Compliance 10/2/2024 Corrections Issued TROY SANDERS