5193 1/4-3/4 W 20TH ST 90016

Certificate Information: 5193 1/4-3/4 W 20TH ST 90016

Application / Permit
22010-30000-03512
Plan Check / Job No.
B22WL02798
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(2) new detached ADU in one building. PER STATED LAW EXISTING MULTIFAMILY
Permit Issued
Issued on 8/12/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 HOOMAN HAJIZADEH
Corrections Issued 8/12/2022 YASHAR EMAMI
Quality Review Completed 8/24/2022 TARIK SAOUD
Building Plans Picked Up 10/3/2022 APPLICANT
Applicant returned to address corrections 7/19/2023 YASHAR EMAMI
Applicant returned to address corrections 8/17/2023 YASHAR EMAMI
Plan Check Approved 9/12/2023 YASHAR EMAMI
Issued 8/12/2024 APPLICANT
CofO in Progress 5/2/2025 ARTHUR NEGRETE
No Progress 5/3/2025 DEROLD HAUFF
CofO in Progress 5/3/2025 DEROLD HAUFF
CofO in Progress 5/22/2025 ARTHUR NEGRETE
Permit Finaled 5/23/2025 DEROLD HAUFF
CofO Issued 5/23/2025 DEROLD HAUFF
Permit Finaled 5/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 12/12/2022 WESTON PRINGLE
Address approval Cleared 12/20/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/22/2022 TREVOR QUAN
Sewer availability Cleared 12/22/2022 TREVOR QUAN
Hydrant and Access approval Cleared 2/16/2023 LAVEON RIDER
Low Impact Development Cleared 8/14/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/18/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2024 Approved ARTHUR NEGRETE
Underground Mechanical 10/18/2024 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 10/25/2024 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 10/25/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/18/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 12/18/2024 Approved ARTHUR NEGRETE
Green Building Rough 12/18/2024 Approved ARTHUR NEGRETE
HVAC-Rough 12/18/2024 Corrections Issued ARTHUR NEGRETE
Verify Sprinkler Sign Off 12/18/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 12/19/2024 Approved ARTHUR NEGRETE
HVAC-Rough 12/19/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 12/19/2024 Approved ARTHUR NEGRETE
Insulation 1/21/2025 Approved ALEX COLIN
Interior/Exterior Lathing 1/21/2025 Partial Approval ALEX COLIN
Sewer 1/24/2025 Approved ARTHUR NEGRETE
Underground Mechanical 1/24/2025 Approved ARTHUR NEGRETE
Drywall Nailing 1/28/2025 Corrections Issued ALEX COLIN
Interior/Exterior Lathing 1/28/2025 Approved ALEX COLIN
Drywall Nailing 1/31/2025 Approved ALEX COLIN
ELECTRICAL-Final 4/22/2025 Approved ARTHUR NEGRETE
Final 4/22/2025 Corrections Issued ARTHUR NEGRETE
Green Building Final 4/22/2025 Approved ARTHUR NEGRETE
HVAC-Final 4/22/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 4/22/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 4/22/2025 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 4/22/2025 Approved ARTHUR NEGRETE
Final 5/1/2025 OK to Issue CofO ARTHUR NEGRETE
Service/Power Release 5/1/2025 Approved ARTHUR NEGRETE