7427 S EL MANOR AVE 90045
Certificate Information: 7427 S EL MANOR AVE 90045
- Application / Permit
- 22010-30000-03508
- Plan Check / Job No.
- B22WL02792
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story SFD w/att garage
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- Current Status
- CofO Issued on 2/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | FELIPE HERNANDEZ |
| Corrections Issued | 8/15/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 8/22/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/22/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/28/2022 | YASHAR EMAMI |
| Plan Check Approved | 10/31/2022 | YASHAR EMAMI |
| Building Plans Picked Up | 10/31/2022 | APPLICANT |
| Issued | 11/1/2022 | APPLICANT |
| CofO in Progress | 2/22/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 2/26/2024 | DANIEL ORRANTE |
| CofO Issued | 2/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 8/14/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2022 | JENSON LEE |
| Sewer availability | Cleared | 8/17/2022 | JENSON LEE |
| Low Impact Development | Cleared | 8/23/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 9/2/2022 | RUEL COLE |
| Trees in Parkway | Cleared | 9/2/2022 | ADALBERTO VERA |
| Specific Plan | Cleared | 9/16/2022 | PEDRO AYALA |
| Address approval | Cleared | 10/24/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 10/31/2022 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 10/31/2022 | KAVIAN REFAHI |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/23/2023 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 6/8/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 6/8/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 6/12/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 8/2/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 8/9/2023 | Corrections Issued | RICHARD STEINBACH |
| HVAC-Rough | 8/9/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 8/9/2023 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 8/29/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/29/2023 | Not Ready for Inspection | HERBERT GIRON |
| Shower Pan | 8/29/2023 | Approved | HERBERT GIRON |
| Special/Order Compliance | 8/29/2023 | Partial Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 8/29/2023 | Approved | HERBERT GIRON |
| Insulation | 9/12/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 9/26/2023 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 9/26/2023 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Final | 1/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 1/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 1/22/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 1/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/22/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 1/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Smoke Detectors | 1/22/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/15/2024 | Approved | TEMISTOCLES CAAL |
| Final | 2/15/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 2/15/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 2/15/2024 | Approved | TEMISTOCLES CAAL |