2038 S GLYNDON AVE 90291
Certificate Information: 2038 S GLYNDON AVE 90291
- Application / Permit
- 22010-30000-03461
- Plan Check / Job No.
- B22WL02752
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD over 1-level basement
- Permit Issued
- Issued on 11/15/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | REZA HAGHIGHAT |
| Corrections Issued | 7/27/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 8/8/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 8/25/2022 | APPLICANT |
| Plan Check Approved | 11/15/2022 | REZA HAGHIGHAT |
| Issued | 11/15/2022 | APPLICANT |
| CofO in Progress | 1/15/2025 | HERBERT GIRON |
| Permit Finaled | 1/23/2025 | RICHARD STEINBACH |
| CofO Issued | 1/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 8/11/2022 | CATHERINE ADROVER |
| Address approval | Cleared | 8/14/2022 | STEVEN JIN |
| Specific Plan | Cleared | 8/16/2022 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 8/17/2022 | SUNG JOON WON |
| Sewer availability | Cleared | 8/17/2022 | DINAH GARIN |
| Trees in Parkway | Cleared | 8/19/2022 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 8/29/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 9/7/2022 | JOHN CONNEALLY |
| SB8 RUD | Cleared | 11/8/2022 | RICHARD TRUONG |
| Excavation more than 5-ft deep | Cleared | 11/15/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Geologist | , ; Lic. No.: GEO2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2023 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 2/23/2023 | Conditional Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 2/24/2023 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 7/3/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 7/25/2023 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/22/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 8/22/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/1/2023 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 10/11/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 2/28/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 2/28/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/4/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 3/4/2024 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 3/4/2024 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 3/15/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 3/15/2024 | Approved | HERBERT GIRON |
| Shower Pan | 3/15/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 3/18/2024 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/9/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 4/9/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | HERBERT GIRON |
| Verify Sprinkler Sign Off | 4/9/2024 | Approved | HERBERT GIRON |
| Insulation | 4/19/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/23/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/13/2024 | Conditional Approval | HERBERT GIRON |
| Drywall Nailing | 5/13/2024 | Approved | HERBERT GIRON |
| Green Building Final | 8/12/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 10/17/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 10/17/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/18/2024 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 10/18/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 10/18/2024 | Approved | HERBERT GIRON |
| Reinforced Concrete Frame | 10/18/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/18/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 10/18/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/2/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 1/2/2025 | Not Ready for Inspection | JESUS PINEDA |
| Final | 1/2/2025 | Corrections Issued | JESUS PINEDA |
| Gas Test | 1/2/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 1/2/2025 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 1/2/2025 | Approved | JESUS PINEDA |
| Service/Power Release | 1/2/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 1/6/2025 | Approved | HERBERT GIRON |
| Final | 1/6/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/6/2025 | Approved | HERBERT GIRON |
| Final | 1/15/2025 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 1/15/2025 | Approved | HERBERT GIRON |