3734 S STEWART AVE 90066
Certificate Information: 3734 S STEWART AVE 90066
- Application / Permit
- 22010-30000-03364
- Plan Check / Job No.
- B22WL02700
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story S.F.D. (2,876 SF) w./ att. 2-car garage (339 SF)
- Permit Issued
- Issued on 10/24/2022
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | TARIK SAOUD |
| Corrections Issued | 7/26/2022 | TARIK SAOUD |
| Quality Review Completed | 8/7/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/21/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 10/24/2022 | REZA HAGHIGHAT |
| Issued | 10/24/2022 | APPLICANT |
| Building Plans Picked Up | 10/24/2022 | APPLICANT |
| CofO in Progress | 8/4/2023 | MICHAEL PELHAM |
| Permit Finaled | 8/8/2023 | DANIEL ORRANTE |
| CofO Issued | 8/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | CATHERINE ADROVER |
| Permit | Cleared | 8/11/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/11/2022 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 8/19/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 9/19/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 9/21/2022 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 9/30/2022 | GILBERT URREA |
| Grading Pre-Inspection | Cleared | 10/20/2022 | TARIK SAOUD |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Not Ready for Inspection | DAVID FEILER |
| Pre-Inspection | 12/29/2022 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 1/25/2023 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 1/25/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 1/25/2023 | Approved | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/9/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/17/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 2/17/2023 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/16/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 3/29/2023 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/18/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/18/2023 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/20/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 4/20/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/20/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/20/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/28/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 4/28/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/28/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 4/28/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/28/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Insulation | 5/2/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/2/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/9/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 5/9/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/9/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/20/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 7/20/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 7/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 7/20/2023 | Approved | JESUS RODRIGUEZ |
| Final | 8/2/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Final | 8/2/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/2/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/2/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/2/2023 | Approved | JESUS RODRIGUEZ |