456 N TUALLITAN ROAD 90049

Certificate Information: 456 N TUALLITAN ROAD 90049

Application / Permit
22010-30000-03362
Plan Check / Job No.
B22WL02690
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 2-story sfd with attached garage
Permit Issued
Issued on 10/31/2022
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 TARIK SAOUD
Corrections Issued 7/26/2022 TARIK SAOUD
Quality Review Completed 8/7/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/4/2022 YASHAR EMAMI
Applicant returned to address corrections 10/18/2022 YASHAR EMAMI
Applicant returned to address corrections 10/21/2022 YASHAR EMAMI
Applicant returned to address corrections 10/28/2022 YASHAR EMAMI
Plan Check Approved 10/31/2022 YASHAR EMAMI
Issued 10/31/2022 APPLICANT
Building Plans Picked Up 11/1/2022 APPLICANT
CofO in Progress 3/28/2024 KEVIN SARGSYAN
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 8/9/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 8/19/2022 LAVEON RIDER
Sewer availability Cleared 8/25/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 8/29/2022 JENSON LEE
Permit Cleared 8/31/2022 JENSON LEE
Low Impact Development Cleared 9/8/2022 ORVAL HERNANDEZ-MARCI
BHO/Hillside ordinance Cleared 9/12/2022 JENSON LEE
BHO/Hillside ordinance Cleared 9/12/2022 JENSON LEE
BHO/Hillside ordinance Cleared 9/12/2022 JENSON LEE
BHO/Hillside ordinance Cleared 9/12/2022 JENSON LEE
BHO/Hillside ordinance Cleared 9/12/2022 JENSON LEE
Roof/Waste drainage to street Cleared 9/19/2022 JENSON LEE
Grading Pre-Inspection Cleared 10/18/2022 TARIK SAOUD
Address approval Cleared 10/20/2022 JENSON LEE

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/12/2023 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 6/12/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 6/13/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 6/13/2023 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 6/16/2023 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 6/16/2023 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 7/5/2023 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval KEVIN SARGSYAN
Sewer 7/17/2023 Approved KEVIN SARGSYAN
Underground Mechanical 8/2/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 8/28/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 9/5/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Partial Approval ARAM AVEDISIAN
Gas Test 9/14/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/14/2023 Approved CARLOS MATAMOROS
Shower Pan 9/20/2023 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 9/27/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/4/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 10/10/2023 Corrections Issued ARAM AVEDISIAN
Green Building Rough 10/10/2023 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 10/10/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/12/2023 Approved ARAM AVEDISIAN
Insulation 10/17/2023 Not Ready for Inspection KEVIN SARGSYAN
Insulation 10/18/2023 Approved ARAM AVEDISIAN
Drywall Nailing 10/27/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/3/2023 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 11/15/2023 Approved DANIEL ORRANTE
HVAC-Final 2/7/2024 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Final 2/14/2024 Partial Approval CARLOS MATAMOROS
Service/Power Release 2/21/2024 Approved CARLOS MATAMOROS
Gas Test 2/28/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 2/28/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 3/13/2024 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 3/13/2024 Approved KEVIN SARGSYAN
Green Building Final 3/13/2024 Approved KEVIN SARGSYAN
HVAC-Final 3/13/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 3/13/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/13/2024 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 3/13/2024 Approved KEVIN SARGSYAN
Final 3/27/2024 OK to Issue CofO KEVIN SARGSYAN