456 N TUALLITAN ROAD 90049
Certificate Information: 456 N TUALLITAN ROAD 90049
- Application / Permit
- 22010-30000-03362
- Plan Check / Job No.
- B22WL02690
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story sfd with attached garage
- Permit Issued
- Issued on 10/31/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | TARIK SAOUD |
| Corrections Issued | 7/26/2022 | TARIK SAOUD |
| Quality Review Completed | 8/7/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/4/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/18/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/21/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/28/2022 | YASHAR EMAMI |
| Plan Check Approved | 10/31/2022 | YASHAR EMAMI |
| Issued | 10/31/2022 | APPLICANT |
| Building Plans Picked Up | 11/1/2022 | APPLICANT |
| CofO in Progress | 3/28/2024 | KEVIN SARGSYAN |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 8/9/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 8/19/2022 | LAVEON RIDER |
| Sewer availability | Cleared | 8/25/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | JENSON LEE |
| Permit | Cleared | 8/31/2022 | JENSON LEE |
| Low Impact Development | Cleared | 9/8/2022 | ORVAL HERNANDEZ-MARCI |
| BHO/Hillside ordinance | Cleared | 9/12/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 9/12/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 9/12/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 9/12/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 9/12/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 10/18/2022 | TARIK SAOUD |
| Address approval | Cleared | 10/20/2022 | JENSON LEE |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/12/2023 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 6/12/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/13/2023 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 6/13/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/16/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/5/2023 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 7/17/2023 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 8/2/2023 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 8/28/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/5/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 9/14/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/14/2023 | Approved | CARLOS MATAMOROS |
| Shower Pan | 9/20/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 9/27/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/10/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Rough | 10/10/2023 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 10/10/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 10/17/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 10/18/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 10/27/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/15/2023 | Approved | DANIEL ORRANTE |
| HVAC-Final | 2/7/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 2/14/2024 | Partial Approval | CARLOS MATAMOROS |
| Service/Power Release | 2/21/2024 | Approved | CARLOS MATAMOROS |
| Gas Test | 2/28/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 2/28/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/13/2024 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/13/2024 | Approved | KEVIN SARGSYAN |
| Green Building Final | 3/13/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 3/13/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 3/13/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 3/13/2024 | Approved | KEVIN SARGSYAN |
| Final | 3/27/2024 | OK to Issue CofO | KEVIN SARGSYAN |