1118-1120 N ANGELO DR 90210

Certificate Information: 1118-1120 N ANGELO DR 90210

Application / Permit
22010-30000-03361
Plan Check / Job No.
B22WL02687
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD (5,225 SF) w./ att. 3-car garage (600 SF) and att. ADU (561 SF) per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 12/9/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 TARIK SAOUD
Corrections Issued 7/18/2022 TARIK SAOUD
Quality Review Completed 7/25/2022 CHIHARU SUZUKI
Building Plans Picked Up 7/25/2022 APPLICANT
Plan Check Approved 11/30/2022 REZA HAGHIGHAT
Issued 12/9/2022 APPLICANT
CofO in Progress 3/11/2025 SEAN HAUPT
CofO Issued 3/15/2025 RICHARD STEINBACH
Permit Finaled 3/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/21/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 7/21/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 7/21/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 7/21/2022 HISASHI KOBAYAKAWA
Miscellaneous Cleared 7/21/2022 SAUL GARCIA
Street Frontage Cleared 7/21/2022 HISASHI KOBAYAKAWA
Address approval Cleared 7/25/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 7/25/2022 HISASHI KOBAYAKAWA
Permit Cleared 7/25/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/4/2022 HISASHI KOBAYAKAWA
Low Impact Development Cleared 8/15/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 8/15/2022 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 8/15/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 8/25/2022 LAVEON RIDER
Construction within easement Cleared 11/22/2022 NADER ISKANDER
Grading Pre-Inspection Cleared 11/30/2022 TARIK SAOUD

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Pillar Building Group Llc; Lic. No.: 1017041-B 8109 ORION AVE      VAN NUYS, CA 91406
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 2/14/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 2/14/2023 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 5/3/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/5/2023 No Access for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/5/2023 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 5/5/2023 No Access for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/8/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 5/8/2023 Partial Approval STEPHANIE SWANSON
Deputy Reinf. Concrete 5/12/2023 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 5/19/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 6/7/2023 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 7/26/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 9/27/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 11/3/2023 Conditional Approval MICHAEL PELHAM
Pre-Inspection 11/8/2023 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 11/27/2023 Not Ready for Inspection BRENDAN LOONEY
Drywall Nailing 12/5/2023 Partial Approval CHRISTOPHER WILSON
Green Building Rough 12/5/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 12/5/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 12/8/2023 Corrections Issued BRENDAN LOONEY
Sewer 12/8/2023 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 12/19/2023 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 12/22/2023 Approved BRENDAN LOONEY
HVAC-Rough 12/22/2023 Approved BRENDAN LOONEY
Sewer 12/22/2023 Approved BRENDAN LOONEY
Special/Order Compliance 12/22/2023 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 1/5/2024 Partial Approval JESUS PINEDA
Shower Pan 1/5/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/12/2024 Corrections Issued BRENDAN LOONEY
Green Building Rough 1/12/2024 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 1/12/2024 Approved BRENDAN LOONEY
Wood Frame 1/12/2024 Partial Approval BRENDAN LOONEY
Insulation 1/30/2024 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 2/16/2024 Approved SEAN HAUPT
Insulation 2/16/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 2/22/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 3/4/2024 Approved SEAN HAUPT
Shower Pan 3/4/2024 Approved SEAN HAUPT
Gas Test 7/2/2024 Approved SEAN HAUPT
Deputy Reinf. Concrete 9/12/2024 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 9/12/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 10/7/2024 Corrections Issued SEAN HAUPT
HVAC-Final 10/7/2024 Not Ready for Inspection SEAN HAUPT
PLUMBING-Final 10/7/2024 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 10/11/2024 Corrections Issued STEPHANIE SWANSON
Gas Test 10/11/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 10/11/2024 Corrections Issued STEPHANIE SWANSON
Service/Power Release 10/11/2024 Approved STEPHANIE SWANSON
Smoke Detectors 10/11/2024 Approved STEPHANIE SWANSON
HVAC-Final 10/18/2024 Approved SEAN HAUPT
PLUMBING-Final 10/18/2024 Approved SEAN HAUPT
ELECTRICAL-Final 1/24/2025 Not Ready for Inspection CHRISTOPHER WILSON
Final 1/24/2025 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 1/24/2025 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 1/24/2025 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 1/24/2025 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 1/24/2025 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Ready CHRISTOPHER WILSON
Final 3/5/2025 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 3/5/2025 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Not Ready CARLOS MATAMOROS
Final 3/10/2025 OK to Issue CofO SEAN HAUPT
Footing/Foundation/Slab 3/10/2025 Approved SEAN HAUPT
Green Building Final 3/10/2025 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Approved SEAN HAUPT