3342 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3342 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22010-30000-03360
- Plan Check / Job No.
- B22WL02685
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD (3,057 sf) w./ att. 2-car garage (339 sf)
- Permit Issued
- Issued on 4/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | REZA HAGHIGHAT |
| Corrections Issued | 7/15/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 7/20/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/16/2022 | APPLICANT |
| Plan Check Approved | 4/12/2023 | REZA HAGHIGHAT |
| Issued | 4/18/2023 | APPLICANT |
| CofO in Progress | 11/13/2024 | DANIEL VERA |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/8/2023 | FREDDY GARCIA |
| Address approval | Cleared | 3/14/2023 | JASON NG |
| Permit | Cleared | 3/14/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | JASON NG |
| Sewer availability | Cleared | 3/20/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 4/2/2023 | KURT CORRAL |
| Trees in Parkway | Cleared | 4/3/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 4/5/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/6/2023 | JASON NG |
| GPI Written Notices | Cleared | 4/12/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 4/12/2023 | REZA HAGHIGHAT |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | 5168 W PICO BLVD LOS ANGELES, CA 90019 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2023 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 6/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/22/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 9/12/2023 | Approved | JESUS PINEDA |
| Sewer | 9/12/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Partial Approval | JESUS PINEDA |
| Shower Pan | 10/6/2023 | Partial Inspection | JESUS PINEDA |
| Shower Pan | 10/11/2023 | Approved | RICHARD STEINBACH |
| Insulation | 10/17/2023 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 10/30/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 10/30/2023 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 11/20/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 11/27/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 11/27/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 11/27/2023 | Not Ready for Inspection | JESUS PINEDA |
| Verify Sprinkler Sign Off | 11/27/2023 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/1/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 12/1/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 12/1/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/5/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 12/5/2023 | Approved | JESUS PINEDA |
| Insulation | 12/21/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 1/3/2024 | Approved | JESUS PINEDA |
| Verify Rec and Parks Fee Memo | 3/28/2024 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 8/26/2024 | Corrections Issued | DANIEL VERA |
| Final | 8/26/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 8/26/2024 | Partial Inspection | DANIEL VERA |
| HVAC-Final | 8/26/2024 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 8/26/2024 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 8/26/2024 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Final | 8/30/2024 | Approved | DANIEL VERA |
| Final | 8/30/2024 | Not Ready for Inspection | DANIEL VERA |
| Gas Test | 8/30/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 8/30/2024 | Approved | DANIEL VERA |
| HVAC-Final | 8/30/2024 | Approved | DANIEL VERA |
| PLUMBING-Final | 8/30/2024 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 8/30/2024 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 8/30/2024 | Approved | DANIEL VERA |
| Final | 9/9/2024 | Not Ready for Inspection | DANIEL VERA |
| Gas Test | 9/9/2024 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 9/9/2024 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 9/9/2024 | Not Ready for Inspection | DANIEL VERA |
| Final | 9/11/2024 | Corrections Issued | DANIEL VERA |
| Gas Test | 9/11/2024 | Approved | DANIEL VERA |
| Service/Power Release | 9/11/2024 | Corrections Issued | DANIEL VERA |
| Final | 11/5/2024 | OK to Issue CofO | DANIEL VERA |
| PLUMBING-Final | 11/5/2024 | Approved | DANIEL VERA |
| Service/Power Release | 11/5/2024 | Approved | DANIEL VERA |