9520 W CRESTA DR 90035
Certificate Information: 9520 W CRESTA DR 90035
- Application / Permit
- 22010-30000-03333
- Plan Check / Job No.
- B22WL02642
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD WITH BASEMENT AND ATTACHED GARAGE.
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | JAHANSHAH POURHASSAN |
| Corrections Issued | 7/26/2022 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 8/8/2022 | TARIK SAOUD |
| Building Plans Picked Up | 8/16/2022 | APPLICANT |
| Applicant returned to address corrections | 12/20/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/3/2023 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/6/2023 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/11/2023 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 1/13/2023 | JAHANSHAH POURHASSAN |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 12/15/2025 | EVAN COOPER |
| CofO in Progress | 12/16/2025 | EVAN COOPER |
| Permit Finaled | 12/18/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/18/2025 | RICHARD STEINBACH |
| CofO Issued | 12/18/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 9/29/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 9/30/2022 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 10/11/2022 | LAVEON RIDER |
| Trees in Parkway | Cleared | 11/18/2022 | ADALBERTO VERA |
| Excavation more than 5-ft deep | Cleared | 1/3/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/11/2023 | JAHANSHAH POURHASSAN |
| Grading Pre-Inspection | Cleared | 1/11/2023 | JAHANSHAH POURHASSAN |
| Low Impact Development | Cleared | 1/13/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/13/2023 | JENSON LEE |
Contact Information
| Architect | Crockett,, Robert York; Lic. No.: C19399 | 373 SOUTH DOHENY DRIVE SUITE A BEVERLY HILLS, CA 90211 |
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Landscape Architect | Alaniz,, Arthur Louis; Lic. No.: LA5554 | 26 CLEAR VISTA ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2023 | Partial Approval | BRENDAN LOONEY |
| METHANE-Barrier | 6/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Subgrade | 6/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 6/20/2023 | Approved | JEREMY TODD |
| Deputy Drilled-In Anchors | 6/30/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 6/30/2023 | Partial Approval | JEREMY TODD |
| METHANE-Barrier | 6/30/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Subgrade | 6/30/2023 | Not Ready for Inspection | JEREMY TODD |
| Deputy Reinf. Concrete | 7/25/2023 | Approved | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 7/25/2023 | Partial Approval | CLAYTON GRAHAM |
| METHANE-Subgrade | 7/25/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Special/Order Compliance | 7/25/2023 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Shotcrete | 7/27/2023 | Conditional Approval | CLAYTON GRAHAM |
| Deputy Shotcrete | 7/28/2023 | Conditional Approval | CLAYTON GRAHAM |
| METHANE-Subgrade | 8/10/2023 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/16/2023 | Partial Approval | DAVID FEILER |
| METHANE-Barrier | 8/16/2023 | Not Ready for Inspection | DAVID FEILER |
| Deputy Methane Barrier | 8/21/2023 | Conditional Approval | DAVID FEILER |
| Deputy Methane Barrier | 8/22/2023 | Conditional Approval | DAVID FEILER |
| Deputy Other (see comments) | 8/25/2023 | Approved | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 8/25/2023 | Partial Approval | CLAYTON GRAHAM |
| METHANE-Barrier | 8/25/2023 | Approved | CLAYTON GRAHAM |
| Reinforced Concrete Frame | 8/28/2023 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/7/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Steel/Welding | 9/12/2023 | Conditional Approval | CLAYTON GRAHAM |
| Reinforced Concrete Frame | 9/13/2023 | Approved | MEL KHACHATOURIAN |
| Deputy Methane Barrier | 9/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 9/20/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/26/2023 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Wood Construction | 10/4/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 10/14/2023 | Conditional Approval | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 10/14/2023 | Corrections Issued | MICHAEL PELHAM |
| Deputy Wood Construction | 10/26/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/22/2024 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/3/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/3/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/10/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/22/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Rough | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/18/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/18/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 6/26/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 10/21/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Service/Power Release | 10/21/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/28/2025 | Approved | MEL KHACHATOURIAN |
| Service/Power Release | 10/28/2025 | Approved | MEL KHACHATOURIAN |
| Gas Test | 11/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 11/18/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 11/18/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Final | 11/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 11/26/2025 | Approved | ASHLEY THOMPSON |
| Gas Test | 11/26/2025 | Approved | ASHLEY THOMPSON |
| Green Building Final | 11/26/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 11/26/2025 | Approved | ASHLEY THOMPSON |
| Final | 12/10/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 12/15/2025 | Conditional Approval | EVAN COOPER |
| PLUMBING-Final | 12/15/2025 | Approved | EVAN COOPER |
| Final | 12/16/2025 | Corrections Issued | EVAN COOPER |