9520 W CRESTA DR 90035

Certificate Information: 9520 W CRESTA DR 90035

Application / Permit
22010-30000-03333
Plan Check / Job No.
B22WL02642
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD WITH BASEMENT AND ATTACHED GARAGE.
Permit Issued
Issued on 1/17/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 JAHANSHAH POURHASSAN
Corrections Issued 7/26/2022 JAHANSHAH POURHASSAN
Quality Review Completed 8/8/2022 TARIK SAOUD
Building Plans Picked Up 8/16/2022 APPLICANT
Applicant returned to address corrections 12/20/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/3/2023 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/6/2023 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/11/2023 JAHANSHAH POURHASSAN
Plan Check Approved 1/13/2023 JAHANSHAH POURHASSAN
Issued 1/17/2023 APPLICANT
CofO in Progress 12/15/2025 EVAN COOPER
CofO in Progress 12/16/2025 EVAN COOPER
Permit Finaled 12/18/2025 RICHARD STEINBACH
Permit Finaled 12/18/2025 RICHARD STEINBACH
CofO Issued 12/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 9/29/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/30/2022 SAUL GARCIA
Sewer availability Cleared 9/30/2022 SAUL GARCIA
Hydrant and Access approval Cleared 10/11/2022 LAVEON RIDER
Trees in Parkway Cleared 11/18/2022 ADALBERTO VERA
Excavation more than 5-ft deep Cleared 1/3/2023 CALOSHA APPROVED
GPI Written Notices Cleared 1/11/2023 JAHANSHAH POURHASSAN
Grading Pre-Inspection Cleared 1/11/2023 JAHANSHAH POURHASSAN
Low Impact Development Cleared 1/13/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/13/2023 JENSON LEE

Contact Information

Architect Crockett,, Robert York; Lic. No.: C19399 373 SOUTH DOHENY DRIVE SUITE A      BEVERLY HILLS, CA 90211
Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311
Engineer Kim,, Hosang; Lic. No.: C67288 18759 WILLOWTREE LANE      PORTER RANCH, CA 91326
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Landscape Architect Alaniz,, Arthur Louis; Lic. No.: LA5554 26 CLEAR VISTA      ROLLING HILLS ESTATES, CA 90274

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/8/2023 Partial Approval BRENDAN LOONEY
METHANE-Barrier 6/8/2023 Not Ready for Inspection BRENDAN LOONEY
METHANE-Subgrade 6/8/2023 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 6/20/2023 Approved JEREMY TODD
Deputy Drilled-In Anchors 6/30/2023 Approved JEREMY TODD
Footing/Foundation/Slab 6/30/2023 Partial Approval JEREMY TODD
METHANE-Barrier 6/30/2023 Not Ready for Inspection JEREMY TODD
METHANE-Subgrade 6/30/2023 Not Ready for Inspection JEREMY TODD
Deputy Reinf. Concrete 7/25/2023 Approved CLAYTON GRAHAM
Footing/Foundation/Slab 7/25/2023 Partial Approval CLAYTON GRAHAM
METHANE-Subgrade 7/25/2023 Not Ready for Inspection CLAYTON GRAHAM
Special/Order Compliance 7/25/2023 Corrections Issued CLAYTON GRAHAM
Deputy Shotcrete 7/27/2023 Conditional Approval CLAYTON GRAHAM
Deputy Shotcrete 7/28/2023 Conditional Approval CLAYTON GRAHAM
METHANE-Subgrade 8/10/2023 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 8/16/2023 Partial Approval DAVID FEILER
METHANE-Barrier 8/16/2023 Not Ready for Inspection DAVID FEILER
Deputy Methane Barrier 8/21/2023 Conditional Approval DAVID FEILER
Deputy Methane Barrier 8/22/2023 Conditional Approval DAVID FEILER
Deputy Other (see comments) 8/25/2023 Approved CLAYTON GRAHAM
Footing/Foundation/Slab 8/25/2023 Partial Approval CLAYTON GRAHAM
METHANE-Barrier 8/25/2023 Approved CLAYTON GRAHAM
Reinforced Concrete Frame 8/28/2023 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 9/7/2023 Partial Approval CLAYTON GRAHAM
Deputy Steel/Welding 9/12/2023 Conditional Approval CLAYTON GRAHAM
Reinforced Concrete Frame 9/13/2023 Approved MEL KHACHATOURIAN
Deputy Methane Barrier 9/19/2023 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 9/20/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/26/2023 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 10/4/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Partial Approval MEL KHACHATOURIAN
Deputy Reinf. Concrete 10/14/2023 Conditional Approval MICHAEL PELHAM
Verify Sprinkler Sign Off 10/14/2023 Corrections Issued MICHAEL PELHAM
Deputy Wood Construction 10/26/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 3/22/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/22/2024 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/3/2024 Approved OGANES TARAKHCHYAN
Shower Pan 5/3/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/10/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/22/2024 Approved MEL KHACHATOURIAN
Green Building Rough 5/22/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 5/22/2024 Partial Approval MEL KHACHATOURIAN
METHANE-Rough 5/22/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 5/22/2024 Approved MEL KHACHATOURIAN
Insulation 6/18/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 6/18/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 6/26/2024 Approved SEAN HAUPT
ELECTRICAL-Final 10/21/2025 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 10/21/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 10/28/2025 Approved MEL KHACHATOURIAN
Service/Power Release 10/28/2025 Approved MEL KHACHATOURIAN
Gas Test 11/18/2025 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Final 11/18/2025 Approved MEL KHACHATOURIAN
PLUMBING-Final 11/18/2025 Corrections Issued MEL KHACHATOURIAN
Final 11/26/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 11/26/2025 Approved ASHLEY THOMPSON
Gas Test 11/26/2025 Approved ASHLEY THOMPSON
Green Building Final 11/26/2025 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 11/26/2025 Approved ASHLEY THOMPSON
Final 12/10/2025 Not Ready for Inspection ASHLEY THOMPSON
Final 12/15/2025 Conditional Approval EVAN COOPER
PLUMBING-Final 12/15/2025 Approved EVAN COOPER
Final 12/16/2025 Corrections Issued EVAN COOPER