342 N KINGS ROAD 90048

Certificate Information: 342 N KINGS ROAD 90048

Application / Permit
22010-30000-03325
Plan Check / Job No.
B22WL02630
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New three car garage with storage[242sf].
Permit Issued
Issued on 10/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2022 APPLICANT
Assigned to Plan Check Engineer 7/18/2022 EDWIN ESPIN
Corrections Issued 7/19/2022 EDWIN ESPIN
Applicant returned to address corrections 9/16/2022 FERNANDO FLORES
Applicant returned to address corrections 9/20/2022 ADAM HEGAZI
Plan Check Approved 9/30/2022 RICARDO RAMIREZ
Issued 10/3/2022 APPLICANT
CofO in Progress 1/19/2023 MICHAEL LEWIS
Permit Finaled 1/21/2023 DEROLD HAUFF
CofO Issued 1/21/2023 DEROLD HAUFF
Permit Finaled 1/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/15/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 9/16/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 9/20/2022 AMAAN MALIK
Construction near power lines Cleared 9/27/2022 TINA MIRANDA
Construction within easement Cleared 9/27/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2022 Approved MICHAEL LEWIS
METHANE-Barrier 10/20/2022 Approved MICHAEL LEWIS
METHANE-Subgrade 10/20/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/4/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved MICHAEL LEWIS
Green Building Rough 11/4/2022 Approved MICHAEL LEWIS
METHANE-Rough 11/4/2022 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 11/8/2022 Approved MICHAEL LEWIS
Deputy Wood Construction 11/8/2022 Approved MICHAEL LEWIS
METHANE-Rough 11/8/2022 Approved MICHAEL LEWIS
Insulation 11/15/2022 Approved JULIAN AMAYA
Interior/Exterior Lathing 11/15/2022 Approved JULIAN AMAYA
Drywall Nailing 11/29/2022 Approved MICHAEL LEWIS
Final 12/6/2022 Corrections Issued MICHAEL LEWIS
Green Building Final 12/6/2022 Approved MICHAEL LEWIS
METHANE-Final 12/6/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 12/6/2022 Approved MICHAEL LEWIS
Final 1/18/2023 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 1/18/2023 Not Required MICHAEL LEWIS