14464 W RUSTIC CREEK LANE 90272
Certificate Information: 14464 W RUSTIC CREEK LANE 90272
- Application / Permit
- 22010-30000-03247
- Plan Check / Job No.
- B22WL02580
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 1-story ADU (1,200 sf) w. att. trellised roof patio cover (32'-6" x 25'-3") (531 sf) per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 4/4/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/4/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | REZA HAGHIGHAT |
| Corrections Issued | 7/17/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 8/1/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/2/2022 | APPLICANT |
| Plan Check Approved | 4/4/2023 | REZA HAGHIGHAT |
| Issued | 4/4/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | CATHERINE ADROVER |
| Certificate of Compliance | Cleared | 8/23/2022 | SPENCER WEJROWSKI |
| Tract Map conditions | Cleared | 8/23/2022 | SPENCER WEJROWSKI |
| Distance to fire station | Cleared | 9/27/2022 | LAVEON RIDER |
| Hydrant and Access approval | Cleared | 9/27/2022 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 12/22/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 12/27/2022 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 12/27/2022 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 12/28/2022 | ANDRES COVARRUBIAS |
| Flood clearance | Cleared | 1/31/2023 | BRYAN GATHUKA |
| Tract Map conditions | Cleared | 3/29/2023 | SPENCER WEJROWSKI |
| GPI Written Notices | Cleared | 4/4/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 4/4/2023 | REZA HAGHIGHAT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Geologist | , ; Lic. No.: GEO740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/14/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/25/2024 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 1/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 1/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 8/2/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/13/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/13/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 6/24/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 6/24/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 6/24/2025 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/2/2025 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Approved | HERBERT GIRON |
| Green Building Rough | 7/2/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 7/2/2025 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 7/2/2025 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 7/2/2025 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 7/2/2025 | Approved | HERBERT GIRON |
| Insulation | 7/9/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 7/14/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 9/26/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/22/2025 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 12/22/2025 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/6/2026 | Approved | HERBERT GIRON |
| Shower Pan | 1/6/2026 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/16/2026 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 4/16/2026 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 4/16/2026 | Approved | HERBERT GIRON |
| HVAC-Final | 4/16/2026 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 4/16/2026 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 5/11/2026 | Not Ready for Inspection | HERBERT GIRON |
| Final | 5/11/2026 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Final | 5/11/2026 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 5/11/2026 | Not Ready for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Not Ready | HERBERT GIRON |
| Service/Power Release | 5/11/2026 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 5/11/2026 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 5/15/2026 | Conditional Approval | HERBERT GIRON |
| Final | 5/15/2026 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 5/15/2026 | Approved | HERBERT GIRON |
| HVAC-Final | 5/15/2026 | Approved | HERBERT GIRON |
| PLUMBING-Final | 5/15/2026 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 5/15/2026 | Not Required | HERBERT GIRON |
| Smoke Detectors | 5/15/2026 | Approved | HERBERT GIRON |