Major remodel and 2-story addition (998 sf) to (e) single story SFD (1,428 sf) (4 bedroom ; 3 bathroom), add an att. 2-car garage (343 sf) at front and add an att. patio cover at rear (10" - 5 1/2" x 16' - 10 1/2 ")
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
CofO Issued on 9/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 REZA HAGHIGHAT
Corrections Issued 7/9/2022 REZA HAGHIGHAT
Quality Review Completed 7/20/2022 CHIHARU SUZUKI
Plan Check Approved 8/31/2022 REZA HAGHIGHAT
Issued 9/1/2022 APPLICANT
Building Plans Picked Up 9/8/2022 APPLICANT
CofO in Progress 9/2/2023 CLAYTON GRAHAM
Permit Finaled 9/8/2023 DANIEL ORRANTE
CofO Issued 9/8/2023 DANIEL ORRANTE
Permit Finaled 9/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 7/27/2022 SARAH YOUSSEF
Trees in Parkway Cleared 8/5/2022 ADALBERTO VERA
Sewer availability Cleared 8/12/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 8/16/2022 JENSON LEE
Permit Cleared 8/16/2022 JENSON LEE
Roof/Waste drainage to street Cleared 8/16/2022 JENSON LEE
GPI Written Notices Cleared 8/31/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 8/31/2022 REZA HAGHIGHAT

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/5/2022 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 12/21/2022 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 12/21/2022 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 12/21/2022 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval JOHNNY MIRANDA
Drywall Nailing 2/23/2023 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Approval JOHNNY MIRANDA
Green Building Rough 2/23/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 2/23/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 3/7/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 3/7/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 3/30/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Approved JESUS RODRIGUEZ
Shower Pan 4/6/2023 Approved CLAYTON GRAHAM
Insulation 4/20/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 4/20/2023 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 4/26/2023 Corrections Issued HERBERT GIRON
Green Building Rough 4/26/2023 Corrections Issued HERBERT GIRON
Insulation 4/26/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 4/26/2023 Partial Approval HERBERT GIRON
MERV13>=Rough 4/26/2023 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 4/28/2023 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 5/5/2023 Approved JOHNNY MIRANDA
Drywall Nailing 5/5/2023 Approved JOHNNY MIRANDA
Green Building Rough 5/5/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/5/2023 Partial Approval JOHNNY MIRANDA
MERV13>=Rough 5/5/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 7/13/2023 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Final 7/13/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Final 7/26/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/26/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 8/2/2023 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 8/2/2023 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 8/8/2023 Approved JESUS PINEDA
HVAC-Final 8/8/2023 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 8/8/2023 Not Ready for Inspection JESUS PINEDA
Final 8/22/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 8/22/2023 Approved JESUS PINEDA
Green Building Final 8/22/2023 Approved JESUS PINEDA
HVAC-Final 8/22/2023 Corrections Issued JESUS PINEDA
MERV13>=Final 8/22/2023 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 8/22/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved JESUS PINEDA
Smoke Detectors 8/22/2023 Approved JESUS PINEDA
Special/Order Compliance 8/22/2023 Partial Inspection BEN MOLSTAD
HVAC-Final 8/29/2023 Approved JESUS PINEDA
Final 9/1/2023 OK to Issue CofO CLAYTON GRAHAM
MERV13>=Final 9/1/2023 Approved CLAYTON GRAHAM
Service/Power Release 9/1/2023 Approved CLAYTON GRAHAM