2525 S HAUSER BLVD A-B 90016
Certificate Information: 2525 S HAUSER BLVD A-B 90016
- Application / Permit
- 22010-30000-03127
- Plan Check / Job No.
- B22WL02488
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- new 3-story Duplex A in front *** 1 of 3 ***
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | KAVIAN REFAHI |
| Corrections Issued | 7/10/2022 | KAVIAN REFAHI |
| Quality Review Completed | 7/11/2022 | TARIK SAOUD |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Plan Check Approved | 12/23/2022 | KAVIAN REFAHI |
| Issued | 1/5/2023 | APPLICANT |
| CofO in Progress | 12/22/2023 | SCOTT FINNILA |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2022 | WALLIE JONG |
| Historic Resource Verification | Cleared | 8/2/2022 | MAX LODER |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | WALLIE JONG |
| Highway dedication | Cleared | 8/4/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 8/4/2022 | KURT CORRAL |
| Frnt yard landscape/Water mgmt | Cleared | 8/8/2022 | RYAN LY |
| Trees in Parkway | Cleared | 8/15/2022 | ADALBERTO VERA |
| Sewer availability | Cleared | 8/16/2022 | WALLIE JONG |
| Redevelopment Project Area | Cleared | 8/17/2022 | DAVID URITA |
| Permit | Cleared | 10/17/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 11/3/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | WALLIE JONG |
| SB8 RUD | Cleared | 12/27/2022 | JESSICA WANG |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD 900 LOS ANGELES, CA 90064 |
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Foroughi,, Mohammad Hossein; Lic. No.: C66179 | 767 NORTH HILL STREET 407 LOS ANGELES, CA 90012 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Corrections Issued | JOSE AVILA |
| Sewer | 2/8/2023 | Partial Inspection | JOSE AVILA |
| Underground Mechanical | 2/8/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 2/15/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 2/15/2023 | Corrections Issued | JOSE AVILA |
| Sewer | 2/15/2023 | Approved | JOSE AVILA |
| Underground Mechanical | 2/15/2023 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 2/17/2023 | Approved | JOSE AVILA |
| Deputy Reinf. Concrete | 2/21/2023 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Corrections Issued | JOSE AVILA |
| Gas Test | 6/8/2023 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 6/8/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/13/2023 | Not Ready for Inspection | JOSE AVILA |
| Shower Pan | 6/13/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 6/22/2023 | Approved | DONALD CRICHLOW |
| ELECTRICAL-Rough | 6/23/2023 | Approved | JOSE AVILA |
| Gas Test | 6/23/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 6/23/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/23/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/26/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 6/26/2023 | Approved | JOSE AVILA |
| MERV13>=Rough | 6/26/2023 | Partial Approval | JOSE AVILA |
| Verify Sprinkler Sign Off | 6/26/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/28/2023 | Partial Approval | JOSE AVILA |
| MERV13>=Rough | 6/28/2023 | Partial Approval | JOSE AVILA |
| Insulation | 6/29/2023 | Corrections Issued | JOSE AVILA |
| Insulation | 7/12/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/12/2023 | Approved | JOSE AVILA |
| Shower Pan | 7/12/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 7/19/2023 | Approved | JOSE AVILA |
| Underground Mechanical | 10/25/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/5/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/5/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/12/2023 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 12/12/2023 | Approved | SCOTT FINNILA |
| HVAC-Final | 12/12/2023 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 12/12/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 12/12/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 12/14/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/14/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/14/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | SCOTT FINNILA |
| Final | 12/19/2023 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 12/19/2023 | Approved | SCOTT FINNILA |
| MERV13>=Final | 12/19/2023 | Approved | SCOTT FINNILA |
| MERV13>=Rough | 12/19/2023 | Approved | SCOTT FINNILA |
| Service/Power Release | 12/19/2023 | Approved | SCOTT FINNILA |
| Smoke Detectors | 12/19/2023 | Approved | SCOTT FINNILA |
| Service/Power Release | 12/22/2023 | Approved | SCOTT FINNILA |