4922 S CENTINELA AVE 1-3 90066

Certificate Information: 4922 S CENTINELA AVE 1-3 90066

Application / Permit
22010-30000-03122
Plan Check / Job No.
B22WL02485
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
new 3 story Duplex with attached ADU and attached garage
Permit Issued
Issued on 4/6/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 TARIK SAOUD
Corrections Issued 7/6/2022 TARIK SAOUD
Quality Review Completed 7/6/2022 KAVIAN REFAHI
Building Plans Picked Up 7/6/2022 APPLICANT
Disabled Access Plans Picked Up 7/18/2022 APPLICANT
Plan Check Approved 8/19/2022 TARIK SAOUD
Issued 4/6/2023 APPLICANT
CofO in Progress 11/22/2024 JESUS PINEDA
Permit Finaled 12/3/2024 RICHARD STEINBACH
CofO Issued 12/3/2024 RICHARD STEINBACH
Permit Finaled 12/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 7/5/2022 HISASHI KOBAYAKAWA
Address approval Cleared 7/6/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 7/6/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 7/6/2022 HISASHI KOBAYAKAWA
Frnt yard landscape/Water mgmt Cleared 7/8/2022 LOUIS ORTEGA
Trees in Parkway Cleared 7/13/2022 ADALBERTO VERA
DAS Clearance Cleared 7/26/2022 CHOI YAN
Hydrant and Access approval Cleared 7/26/2022 KURT CORRAL
Low Impact Development Cleared 8/2/2022 TA ANH
Roof/Waste drainage to street Cleared 8/3/2022 HISASHI KOBAYAKAWA
Specific Plan Cleared 8/9/2022 PEDRO AYALA

Contact Information

Contractor Vickers Construction Company Inc; Lic. No.: 1008338-B 952 E 116TH STREET      LOS ANGELES, CA 90059
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/9/2023 Not Ready for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/17/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 5/17/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 5/25/2023 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/26/2023 Approved JESUS RODRIGUEZ
Deputy Reinf. Concrete 6/2/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 7/20/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 7/20/2023 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 7/20/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 10/24/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 10/24/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 10/24/2023 Corrections Issued JESUS RODRIGUEZ
Verify Sprinkler Sign Off 10/24/2023 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Wood Construction 10/25/2023 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/6/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 11/6/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Approved JESUS RODRIGUEZ
Green Building Rough 11/6/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 11/6/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/6/2023 Corrections Issued JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/6/2023 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/16/2024 Not Ready for Inspection JESUS RODRIGUEZ
Insulation 1/16/2024 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 1/16/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/16/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 1/16/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/22/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 3/22/2024 Approved JESUS RODRIGUEZ
Green Building Rough 3/22/2024 Approved JESUS RODRIGUEZ
Insulation 3/22/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/28/2024 Approved RICHARD STEINBACH
Shower Pan 3/28/2024 Approved RICHARD STEINBACH
Sewer 8/20/2024 Approved JESUS RODRIGUEZ
HVAC-Final 10/29/2024 Corrections Issued JESUS PINEDA
PLUMBING-Final 10/29/2024 Corrections Issued JESUS PINEDA
Service/Power Release 10/29/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 11/13/2024 Corrections Issued JESUS PINEDA
HVAC-Final 11/13/2024 Approved JESUS PINEDA
PLUMBING-Final 11/13/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 11/20/2024 Approved JESUS PINEDA
Final 11/20/2024 Corrections Issued JESUS PINEDA
Gas Test 11/20/2024 Approved JESUS PINEDA
Green Building Final 11/20/2024 Approved JESUS PINEDA
PLUMBING-Final 11/20/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Approved JESUS PINEDA
Service/Power Release 11/20/2024 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 11/20/2024 Approved JESUS PINEDA
Final 11/22/2024 OK to Issue CofO JESUS PINEDA
Service/Power Release 11/22/2024 Approved JESUS PINEDA