1723 N COURTNEY AVE 90046

Certificate Information: 1723 N COURTNEY AVE 90046

Application / Permit
22010-30000-03098
Plan Check / Job No.
B22WL02437
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story S.F.D. (2,802 sf) w/ att. 2-car garage (339 sf) ; (4-bedroom ; 4-bathroom)
Permit Issued
Issued on 9/15/2022
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 REZA HAGHIGHAT
Corrections Issued 7/5/2022 REZA HAGHIGHAT
Quality Review Completed 7/5/2022 KAVIAN REFAHI
Building Plans Picked Up 7/6/2022 APPLICANT
Plan Check Approved 9/14/2022 REZA HAGHIGHAT
Issued 9/15/2022 APPLICANT
CofO in Progress 12/22/2023 BRIAN SULLIVAN
Permit Finaled 12/29/2023 DEROLD HAUFF
CofO Issued 12/29/2023 DEROLD HAUFF
Permit Finaled 12/29/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/12/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 7/12/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 7/12/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 7/12/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 7/12/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/12/2022 JEANETTE VONG
Permit Cleared 7/12/2022 JEANETTE VONG
Sewer availability Cleared 7/12/2022 JEANETTE VONG
ZA Case Cleared 7/12/2022 ANACANY HURTADO
Low Impact Development Cleared 8/3/2022 MARCO SANCHEZ
Hydrant and Access approval Cleared 8/5/2022 RUEL COLE
Roof/Waste drainage to street Cleared 8/5/2022 JEANETTE VONG
GPI Written Notices Cleared 9/10/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 9/10/2022 REZA HAGHIGHAT
Trees in Parkway Cleared 9/13/2022 ADALBERTO VERA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/1/2023 Approved BRIAN SULLIVAN
Underground Mechanical 6/1/2023 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 6/13/2023 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 6/15/2023 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval STUART CHAPMAN
Deputy Wood Construction 8/8/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Corrections Issued STUART CHAPMAN
HVAC-Rough 8/8/2023 Approved STUART CHAPMAN
Deputy Wood Construction 8/11/2023 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 8/11/2023 Approved BRIAN SULLIVAN
Deputy Wood Construction 8/14/2023 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 8/25/2023 Approved BRIAN SULLIVAN
Shower Pan 8/25/2023 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 8/28/2023 Approved BRIAN SULLIVAN
Green Building Rough 8/28/2023 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 8/28/2023 Approved BRIAN SULLIVAN
Insulation 9/5/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/5/2023 Partial Approval BRIAN SULLIVAN
Drywall Nailing 9/13/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/13/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Final 11/20/2023 Approved BRIAN SULLIVAN
Gas Test 11/20/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 11/20/2023 Approved BRIAN SULLIVAN
Service/Power Release 11/20/2023 Not Ready for Inspection BRIAN SULLIVAN
Verify Rec and Parks Fee Memo 11/28/2023 Approved BRIAN SULLIVAN
Service/Power Release 11/29/2023 Approved MICHAEL PELHAM
Final 12/4/2023 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 12/4/2023 Approved BRIAN SULLIVAN
Gas Test 12/4/2023 Approved BRIAN SULLIVAN
Green Building Final 12/4/2023 Approved BRIAN SULLIVAN
HVAC-Final 12/4/2023 Approved BRIAN SULLIVAN
PLUMBING-Final 12/4/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 12/4/2023 Approved BRIAN SULLIVAN
Smoke Detectors 12/4/2023 Approved BRIAN SULLIVAN
Final 12/8/2023 Corrections Issued BRIAN SULLIVAN
Final 12/21/2023 OK to Issue CofO BRIAN SULLIVAN