1130-1130 1/2 E 28TH ST 90011

Certificate Information: 1130-1130 1/2 E 28TH ST 90011

Application / Permit
22010-30000-03065
Plan Check / Job No.
B22WL02430
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
2-STORY TYPE VB DUPLEX, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 11/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 SERGIO SILVA
Corrections Issued 7/20/2022 SERGIO SILVA
Quality Review Completed 7/27/2022 CHIHARU SUZUKI
Plan Check Approved 11/2/2022 SERGIO SILVA
Building Plans Picked Up 11/4/2022 APPLICANT
Issued 11/14/2022 APPLICANT
CofO in Progress 9/30/2023 ALEJANDRO DE ARTOLA
CofO Issued 10/9/2023 DEROLD HAUFF
Permit Finaled 10/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/9/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/10/2022 JEANIE LAM
Sewer availability Cleared 8/10/2022 JEANIE LAM
Trees in Parkway Cleared 9/6/2022 ADALBERTO VERA
Frnt yard landscape/Water mgmt Cleared 9/14/2022 CLAUDE GOODING
Hydrant and Access approval Cleared 9/18/2022 JOHN CONNEALLY
Low Impact Development Cleared 9/26/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/3/2022 JEANIE LAM
Permit Cleared 10/18/2022 JEANIE LAM

Contact Information

Architect , ; Lic. No.: C35150       ,
Contractor Moreno Chris; Lic. No.: 973501-B 1158 W 126TH STREET      LOS ANGELES, CA 90044
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 12/27/2022 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/19/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 1/19/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Approved BRENDAN MORELLI
HVAC-Rough 3/29/2023 Conditional Approval BRENDAN MORELLI
PLUMBING-Rough 3/29/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 3/30/2023 Approved BRENDAN MORELLI
ELECTRICAL-Rough 3/30/2023 Approved BRENDAN MORELLI
Green Building Rough 3/30/2023 Approved BRENDAN MORELLI
HVAC-Rough 3/30/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 3/30/2023 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 3/30/2023 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 3/30/2023 Approved BRENDAN MORELLI
Insulation 4/4/2023 Approved BRENDAN MORELLI
Drywall Nailing 4/17/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 4/17/2023 Approved BRENDAN MORELLI
Sewer 6/7/2023 Approved BRENDAN MORELLI
Underground Mechanical 6/7/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 9/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/28/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/29/2023 Approved ALEJANDRO DE ARTOLA
Final 9/29/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 9/29/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 9/29/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 9/29/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 9/29/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 9/29/2023 Approved ALEJANDRO DE ARTOLA