7444 N TAMPA AVE 91335
Certificate Information: 7444 N TAMPA AVE 91335
- Application / Permit
- 22010-30000-02930
- Plan Check / Job No.
- B22WL02352
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- proposed 2-story ADU per ordinance. ** see comments**
- Permit Issued
- Issued on 10/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | KAVIAN REFAHI |
| Corrections Issued | 6/25/2022 | KAVIAN REFAHI |
| Quality Review Completed | 7/7/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 9/16/2022 | KAVIAN REFAHI |
| Plan Check Approved | 10/12/2022 | KAVIAN REFAHI |
| Issued | 10/18/2022 | APPLICANT |
| Building Plans Picked Up | 10/20/2022 | APPLICANT |
| CofO in Progress | 10/24/2023 | JEFFREY BULL |
| Permit Finaled | 11/27/2023 | JOHN JANSON |
| CofO Issued | 11/27/2023 | JOHN JANSON |
| Permit Finaled | 11/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2022 | JOSE DUARTE-DIAZ |
| Construction within easement | Cleared | 6/30/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 8/11/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/11/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 9/2/2022 | KURT CORRAL |
Contact Information
| Contractor | S P S Construction; Lic. No.: 683130-B | 10153 1/2 RIVERSIDE DR APT 463 TOLUCA LAKE, CA 91602 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 11/4/2022 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 11/7/2022 | Partial Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 11/14/2022 | Approved | JEFFREY BULL |
| Wood Frame | 11/29/2022 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 12/16/2022 | Not Ready for Inspection | SEAN HAUPT |
| Sewer | 12/16/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 12/19/2022 | Not Ready for Inspection | JEFFREY BULL |
| Sewer | 12/19/2022 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 12/27/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 12/27/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 12/27/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 1/10/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 1/10/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 1/10/2023 | Approved | JEFFREY BULL |
| Wood Frame | 1/10/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 1/13/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/13/2023 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 1/17/2023 | Corrections Issued | JEFFREY BULL |
| Drywall Nailing | 1/20/2023 | Approved | JEFFREY BULL |
| Shower Pan | 1/25/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/30/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 10/18/2023 | Approved | JEFFREY BULL |
| Final | 10/18/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 10/18/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 10/18/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 10/18/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 10/18/2023 | Not Required | JEFFREY BULL |
| Smoke Detectors | 10/18/2023 | Not Ready for Inspection | JEFFREY BULL |
| Verify Sprinkler Sign Off | 10/18/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 10/20/2023 | Approved | JEFFREY BULL |
| Final | 10/20/2023 | OK to Issue CofO | JEFFREY BULL |
| HVAC-Final | 10/20/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 10/20/2023 | Approved | JEFFREY BULL |
| Service/Power Release | 10/20/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 10/20/2023 | Approved | JEFFREY BULL |