6112-6114 E MERIDIAN ST 90042
Certificate Information: 6112-6114 E MERIDIAN ST 90042
- Application / Permit
- 22010-30000-02877
- Plan Check / Job No.
- B22WL02308
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY TYPE VB DUPLEX WITH ATTACHED GARAGE AND ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 1/20/2023
- Issuing Office
- Current Status
- CofO Issued on 6/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | TARIK SAOUD |
| Corrections Issued | 7/6/2022 | TARIK SAOUD |
| Quality Review Completed | 7/6/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/20/2022 | SERGIO SILVA |
| Plan Check Approved | 11/7/2022 | SERGIO SILVA |
| Issued | 1/20/2023 | APPLICANT |
| Building Plans Picked Up | 1/31/2023 | APPLICANT |
| CofO in Progress | 6/15/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 6/27/2024 | DEROLD HAUFF |
| Permit Finaled | 6/27/2024 | DEROLD HAUFF |
| CofO Issued | 6/27/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | JEANIE LAM |
| Sewer availability | Cleared | 7/19/2022 | JEANIE LAM |
| Trees in Parkway | Cleared | 8/4/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 8/5/2022 | RUEL COLE |
| Frnt yard landscape/Water mgmt | Cleared | 8/10/2022 | BRENNEN OBETO |
| Highway dedication | Cleared | 8/25/2022 | JEANIE LAM |
| DAS Clearance | Cleared | 9/21/2022 | TARIK SAOUD |
| Low Impact Development | Cleared | 9/23/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/24/2022 | JEANETTE VONG |
| GPI Written Notices | Cleared | 10/12/2022 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 10/12/2022 | TARIK SAOUD |
| Permit | Cleared | 11/2/2022 | TREVOR QUAN |
Contact Information
| Contractor | Onward Builders Llc; Lic. No.: 1084275-B | 750 N SAN VICENTE BLVD STE 800 WEST HOLLYWOOD, CA 90069 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Landscape Architect | Alaniz,, Arthur Louis; Lic. No.: LA5554 | 26 CLEAR VISTA ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 4/12/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/18/2023 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 4/18/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 4/20/2023 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/25/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/7/2023 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/18/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/20/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/20/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/10/2023 | Approved | CRAIG VAUGHAN |
| Shower Pan | 8/10/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 8/10/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Shower Pan | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 8/30/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/7/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 9/7/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/13/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/6/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Gas Test | 5/6/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/6/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/6/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/31/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/4/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 6/4/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/14/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 6/14/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/24/2024 | Approved | ALIZAH MAYAGOITIA |