2708 W SAXON DR 90065

Certificate Information: 2708 W SAXON DR 90065

Application / Permit
22010-30000-02837
Plan Check / Job No.
B22WL02273
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-story det. ADU (497 sf) w./ att. trellised roof patio cover (177 sf) per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/9/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 YASHAR EMAMI
Corrections Issued 6/17/2022 YASHAR EMAMI
Quality Review Completed 7/5/2022 TARIK SAOUD
Applicant returned to address corrections 9/20/2022 YASHAR EMAMI
Applicant returned to address corrections 10/17/2022 YASHAR EMAMI
Applicant returned to address corrections 10/21/2022 YASHAR EMAMI
Applicant returned to address corrections 10/31/2022 YASHAR EMAMI
Applicant returned to address corrections 11/8/2022 YASHAR EMAMI
Building Plans Picked Up 11/8/2022 APPLICANT
Plan Check Approved 12/9/2022 YASHAR EMAMI
Issued 12/9/2022 APPLICANT
CofO in Progress 6/5/2023 CRAIG VAUGHAN
CofO Issued 6/8/2023 DEROLD HAUFF
Permit Finaled 6/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/23/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/23/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/23/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/23/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/23/2022 CINDY QI
Permit Cleared 7/23/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/28/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/5/2022 CINDY QI
Community Plan Implem. Overlay Cleared 8/10/2022 KEVIN ARUCAN
Sewer availability Cleared 8/10/2022 CINDY QI
Hydrant and Access approval Cleared 8/23/2022 RUEL COLE
Low Impact Development Cleared 9/16/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/16/2022 CINDY QI
GPI Written Notices Cleared 9/20/2022 YASHAR EMAMI
Grading Pre-Inspection Cleared 9/20/2022 YASHAR EMAMI
Construction near power lines Cleared 10/4/2022 TINA MIRANDA
Construction within easement Cleared 10/4/2022 TINA MIRANDA
Miscellaneous Cleared 12/7/2022 YASHAR EMAMI

Contact Information

Contractor Yakov Design & Build; Lic. No.: 1067993-B 5535 WESTLAWN AVE APT 376      LOS ANGELES, CA 90066
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2022 No Access for Inspection CRAIG VAUGHAN
Sewer 12/15/2022 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 12/19/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 12/19/2022 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/22/2022 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 1/12/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 1/12/2023 Not Ready for Inspection CRAIG VAUGHAN
MERV13>=Rough 1/12/2023 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 1/12/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/1/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 2/1/2023 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 2/1/2023 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 2/1/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/7/2023 Approved CRAIG VAUGHAN
HVAC-Rough 3/7/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/7/2023 Approved CRAIG VAUGHAN
Sewer 3/7/2023 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 3/7/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/9/2023 Approved CRAIG VAUGHAN
Green Building Rough 3/9/2023 Approved CRAIG VAUGHAN
HVAC-Rough 3/9/2023 Approved CRAIG VAUGHAN
MERV13>=Rough 3/9/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/9/2023 Approved CRAIG VAUGHAN
Sewer 3/9/2023 Approved CRAIG VAUGHAN
Underground Mechanical 3/9/2023 Partial Approval CRAIG VAUGHAN
Verify Sprinkler Sign Off 3/9/2023 Approved CRAIG VAUGHAN
Wood Frame 3/9/2023 Approved CRAIG VAUGHAN
Insulation 3/14/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/14/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 3/20/2023 Not Ready for Inspection CRAIG VAUGHAN
Sewer 3/20/2023 Approved CRAIG VAUGHAN
Wood Frame 3/20/2023 Approved CRAIG VAUGHAN
Drywall Nailing 3/22/2023 Approved CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 3/22/2023 Approved CHARLES BOGHOSKHAN
Shower Pan 3/22/2023 Approved CHARLES BOGHOSKHAN
Wood Frame 3/22/2023 Approved CHARLES BOGHOSKHAN
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Not Ready SCOTT FINNILA
Final 5/25/2023 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 5/25/2023 No Access for Inspection SCOTT FINNILA
ELECTRICAL-Final 5/31/2023 Corrections Issued CRAIG VAUGHAN
Final 5/31/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 5/31/2023 Approved CRAIG VAUGHAN
HVAC-Final 5/31/2023 Approved CRAIG VAUGHAN
MERV13>=Final 5/31/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 5/31/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 5/31/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 6/2/2023 Approved CRAIG VAUGHAN
Final 6/2/2023 OK to Issue CofO CRAIG VAUGHAN
Footing/Foundation/Slab 6/2/2023 Approved CRAIG VAUGHAN
Service/Power Release 6/2/2023 Approved CRAIG VAUGHAN