735 E 82ND ST 90001

Certificate Information: 735 E 82ND ST 90001

Application / Permit
22010-30000-02820
Plan Check / Job No.
B22WL02261
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU over garage per ordinance ** 2 of 2 **
Permit Issued
Issued on 8/4/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 KAVIAN REFAHI
Corrections Issued 9/15/2022 KAVIAN REFAHI
Quality Review Completed 9/20/2022 CHIHARU SUZUKI
Building Plans Picked Up 9/21/2022 APPLICANT
Applicant returned to address corrections 1/11/2023 KAVIAN REFAHI
Plan Check Approved 7/17/2023 KAVIAN REFAHI
No Progress 7/17/2023 KAVIAN REFAHI
Plan Check Approved 7/17/2023 KAVIAN REFAHI
Issued 8/4/2023 APPLICANT
CofO in Progress 11/5/2024 MICHAEL LEWIS
Permit Finaled 11/21/2024 DEROLD HAUFF
CofO Issued 11/21/2024 DEROLD HAUFF
Permit Finaled 11/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/22/2022 CHRIS VONG
SB8 RUD Cleared 9/22/2022 JESSICA WANG
Hydrant and Access approval Cleared 9/30/2022 LAVEON RIDER
Address approval Cleared 10/3/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 10/3/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/13/2022 CELINA MORENO
Sewer availability Cleared 10/13/2022 CELINA MORENO
Construction near power lines Cleared 6/2/2023 RIDWAN HARDY

Contact Information

Architect , ; Lic. No.: C35150 2355 WESTWOOD BLVD   900    LOS ANGELES, CA 90064
Contractor Moreno Chris; Lic. No.: 973501-B 1158 W 126TH STREET      LOS ANGELES, CA 90044
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/26/2023 Corrections Issued DAVID FEILER
Underground Mechanical 1/2/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 2/14/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 2/14/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 6/20/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 6/20/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 6/21/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 6/21/2024 Approved MICHAEL LEWIS
Green Building Rough 6/21/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 6/21/2024 Approved MICHAEL LEWIS
Insulation 6/24/2024 Approved MICHAEL LEWIS
Drywall Nailing 7/19/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/19/2024 Approved MICHAEL LEWIS
Sewer 8/20/2024 Approved MICHAEL LEWIS
Underground Mechanical 8/20/2024 Approved MICHAEL LEWIS
HVAC-Final 11/1/2024 Approved MICHAEL LEWIS
PLUMBING-Final 11/1/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 11/4/2024 Approved MICHAEL LEWIS
Final 11/4/2024 OK to Issue CofO MICHAEL LEWIS
Green Building Final 11/4/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/4/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 11/4/2024 Approved MICHAEL LEWIS
Smoke Detectors 11/4/2024 Approved MICHAEL LEWIS
HVAC-Final 11/12/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 11/18/2024 Approved MICHAEL LEWIS