1614 1/2 S SYCAMORE AVE 90019
Certificate Information: 1614 1/2 S SYCAMORE AVE 90019
- Application / Permit
- 22010-30000-02681
- Plan Check / Job No.
- B22WL02151
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story ADU (760 sf) (2-bedroom ; 2-bathroom) in the middle of the lot per LAMC 12.22 A.33 (c) - (d)
- Permit Issued
- Issued on 11/30/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | REZA HAGHIGHAT |
| Corrections Issued | 6/29/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 7/5/2022 | TARIK SAOUD |
| Building Plans Picked Up | 7/6/2022 | APPLICANT |
| Plan Check Approved | 2/27/2023 | REZA HAGHIGHAT |
| Issued | 11/30/2023 | APPLICANT |
| CofO in Progress | 2/19/2025 | ARTHUR NEGRETE |
| CofO in Progress | 2/21/2025 | ARTHUR NEGRETE |
| Permit Finaled | 3/26/2025 | DEROLD HAUFF |
| CofO Issued | 3/26/2025 | DEROLD HAUFF |
| Permit Finaled | 3/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 7/19/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 7/26/2022 | KURT CORRAL |
| Flood clearance | Cleared | 8/22/2022 | BRYAN GATHUKA |
| Frnt yard landscape/Water mgmt | Cleared | 8/24/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 8/24/2022 | MAXFIELD VERMY |
| Prkng lot landscape/Water mgmt | Cleared | 8/24/2022 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 11/8/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/15/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 12/14/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 12/14/2023 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 12/14/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 12/14/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 12/14/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| FLOOD-Elevation Certificate | 1/2/2024 | Partial Inspection | STUART CHAPMAN |
| Final | 1/2/2024 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2024 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 1/2/2024 | Conditional Approval | STUART CHAPMAN |
| METHANE-Barrier | 1/2/2024 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 1/2/2024 | Approved | STUART CHAPMAN |
| Underground Mechanical | 1/24/2024 | No Access for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 1/26/2024 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Corrections Issued | RICHARD DOCKUS |
| Deputy Wood Construction | 4/12/2024 | Conditional Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 5/9/2024 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/21/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/21/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 5/29/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | WILLIAM KUEHN |
| FLOOD-Proofing Certificate | 6/20/2024 | Approved | WILLIAM KUEHN |
| Green Building Rough | 6/20/2024 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 6/20/2024 | Partial Approval | WILLIAM KUEHN |
| METHANE-Rough | 6/20/2024 | Approved | WILLIAM KUEHN |
| Shower Pan | 6/20/2024 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 6/20/2024 | Approved | WILLIAM KUEHN |
| Wood Frame | 6/20/2024 | Approved | WILLIAM KUEHN |
| Insulation | 6/27/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 6/27/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 7/9/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 12/18/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 12/18/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 12/18/2024 | Approved | ARTHUR NEGRETE |
| FLOOD-Elevation Certificate | 2/18/2025 | Approved | ARTHUR NEGRETE |
| Final | 2/18/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 2/18/2025 | Approved | ARTHUR NEGRETE |
| Gas Test | 2/18/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 2/18/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 2/18/2025 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 2/18/2025 | Approved | ARTHUR NEGRETE |
| Final | 2/20/2025 | OK to Issue CofO | ARTHUR NEGRETE |