3212 S PHILO ST 90064
Certificate Information: 3212 S PHILO ST 90064
- Application / Permit
- 22010-30000-02675
- Plan Check / Job No.
- B22WL02143
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story detached ADU w/ roof trusses per Govt, Code
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | HOOMAN HAJIZADEH |
| Corrections Issued | 6/10/2022 | HOOMAN HAJIZADEH |
| Quality Review Completed | 7/1/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 10/25/2022 | HOOMAN HAJIZADEH |
| Plan Check Approved | 11/18/2022 | HOOMAN HAJIZADEH |
| Issued | 11/21/2022 | APPLICANT |
| Building Plans Picked Up | 11/21/2022 | APPLICANT |
| CofO in Progress | 1/8/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
| CofO Issued | 1/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/8/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | DINAH GARIN |
| Sewer availability | Cleared | 7/12/2022 | DINAH GARIN |
| ZI | Cleared | 7/12/2022 | BRENNEN OBETO |
| Specific Plan | Cleared | 8/17/2022 | FREDDY GARCIA |
| Construction near power lines | Cleared | 8/31/2022 | TINA MIRANDA |
| GPI Written Notices | Cleared | 10/25/2022 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 10/25/2022 | HOOMAN HAJIZADEH |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/25/2023 | Partial Approval | CLAYTON GRAHAM |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Approved | CLAYTON GRAHAM |
| Underground Mechanical | 5/24/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 6/2/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 6/2/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 6/2/2023 | Approved | CLAYTON GRAHAM |
| MERV13>=Rough | 6/2/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 6/2/2023 | Approved | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 6/2/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 6/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Wood Construction | 6/8/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 6/12/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| MERV13>=Rough | 6/12/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 6/12/2023 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 6/12/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 6/26/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 6/26/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 7/6/2023 | No Access for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 7/11/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 7/11/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 7/11/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | CLAYTON GRAHAM |
| Drywall Nailing | 7/19/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 9/6/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 9/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 10/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 10/16/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 10/16/2023 | Approved | CLAYTON GRAHAM |
| Green Building Final | 10/16/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 10/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| MERV13>=Final | 10/16/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 10/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Service/Power Release | 10/16/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Smoke Detectors | 10/16/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 10/23/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 10/23/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Final | 10/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Gas Test | 10/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 10/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 10/27/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 10/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Service/Power Release | 10/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Gas Test | 11/15/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 11/15/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 11/15/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 11/27/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 12/6/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 12/6/2023 | Approved | OGANES TARAKHCHYAN |