6132 W MARYLAND DR 90048

Certificate Information: 6132 W MARYLAND DR 90048

Application / Permit
22010-30000-02571
Plan Check / Job No.
B22WL02027
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New detached Garage w./ att. half bathroom at rear of the lot (370 sf)
Permit Issued
Issued on 9/29/2022
Issuing Office
Current Status
CofO Issued on 6/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 REZA HAGHIGHAT
Corrections Issued 6/5/2022 REZA HAGHIGHAT
Quality Review Completed 6/7/2022 CHIHARU SUZUKI
Plan Check Approved 9/29/2022 REZA HAGHIGHAT
Issued 9/29/2022 APPLICANT
Building Plans Picked Up 10/3/2022 APPLICANT
CofO in Progress 5/28/2024 MEL KHACHATOURIAN
Permit Finaled 6/5/2024 DANIEL ORRANTE
CofO Issued 6/5/2024 DANIEL ORRANTE
Permit Finaled 6/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/16/2022 AMAAN MALIK
Permit Cleared 6/16/2022 AMAAN MALIK
Sewer availability Cleared 6/16/2022 AMAAN MALIK
CPC Cleared 7/13/2022 JAZMIN ROQUE
ZI Cleared 7/13/2022 JAZMIN ROQUE
Construction within easement Cleared 8/15/2022 RIDWAN HARDY
Trees in Parkway Cleared 8/17/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 8/19/2022 JEANIE LAM

Contact Information

Contractor Refined Home Construction Inc; Lic. No.: 1001310-B 113 N SAN VICENTE BLVD      BEVERLY HILLS, CA 90211
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/1/2022 Corrections Issued EVAN COOPER
METHANE-Barrier 11/1/2022 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 11/1/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 11/1/2022 Corrections Issued EVAN COOPER
Sewer 11/1/2022 Approved EVAN COOPER
Footing/Foundation/Slab 11/3/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 11/10/2022 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 11/10/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/16/2023 Approved CLAYTON GRAHAM
PLUMBING-Rough 2/16/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Approved JEREMY TODD
HVAC-Rough 2/27/2023 Not Ready for Inspection JEREMY TODD
PLUMBING-Rough 2/27/2023 Partial Approval JEREMY TODD
Shower Pan 3/1/2023 Approved JEREMY TODD
Interior/Exterior Lathing 3/6/2023 Approved JEREMY TODD
Green Building Rough 6/15/2023 Approved JEREMY TODD
Insulation 6/15/2023 Conditional Approval JEREMY TODD
Drywall Nailing 6/22/2023 Approved JEREMY TODD
Interior/Exterior Lathing 6/30/2023 Partial Approval BRENDAN LOONEY
ELECTRICAL-Final 11/29/2023 Partial Approval MEL KHACHATOURIAN
PLUMBING-Final 11/29/2023 Partial Approval MEL KHACHATOURIAN
Service/Power Release 4/1/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/29/2024 Approved MEL KHACHATOURIAN
Final 5/29/2024 OK to Issue CofO MEL KHACHATOURIAN
Footing/Foundation/Slab 5/29/2024 Approved MEL KHACHATOURIAN
Green Building Final 5/29/2024 Approved MEL KHACHATOURIAN
METHANE-Barrier 5/29/2024 Approved MEL KHACHATOURIAN
METHANE-Final 5/29/2024 Approved MEL KHACHATOURIAN
METHANE-Rough 5/29/2024 Approved MEL KHACHATOURIAN
METHANE-Subgrade 5/29/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 5/29/2024 Approved MEL KHACHATOURIAN
Smoke Detectors 5/29/2024 Approved MEL KHACHATOURIAN