1972 1/2 E 112TH ST 90059

Certificate Information: 1972 1/2 E 112TH ST 90059

Application / Permit
22010-30000-02439
Plan Check / Job No.
B22WL01931
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1-STORY TYPE VB ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 5/18/2023
Issuing Office
San Pedro
Current Status
Issued on 5/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/19/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 SERGIO SILVA
Corrections Issued 6/15/2022 SERGIO SILVA
Quality Review Completed 6/27/2022 TARIK SAOUD
Applicant returned to address corrections 1/18/2023 SERGIO SILVA
Building Plans Picked Up 1/24/2023 APPLICANT
Applicant returned to address corrections 2/24/2023 SERGIO SILVA
Applicant returned to address corrections 3/20/2023 SERGIO SILVA
Applicant returned to address corrections 4/3/2023 SERGIO SILVA
Plan Check Approved 5/8/2023 SERGIO SILVA
Issued 5/18/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/21/2022 CINDY QI
Permit Cleared 7/21/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/28/2022 CINDY QI
Trees in Parkway Cleared 8/15/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 8/20/2022 RUEL COLE
Low Impact Development Cleared 10/28/2022 MARTIN FRAGOSO
Sewer availability Cleared 10/31/2022 CINDY QI
Roof/Waste drainage to street Cleared 11/1/2022 CINDY QI
Construction near power lines Cleared 11/15/2022 TINA MIRANDA
Green Code Cleared 1/18/2023 SERGIO SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2023 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/24/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 7/24/2023 Corrections Issued JOHN KLARIN
PLUMBING-Rough 8/4/2023 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 9/28/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 9/28/2023 Approved JOHN KLARIN
Green Building Rough 9/28/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 9/28/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 9/28/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/12/2023 Approved JOHN KLARIN
Green Building Rough 10/12/2023 Approved JOHN KLARIN
Wood Frame 10/12/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 10/23/2023 Partial Approval JAMES CHAVEZ
Gas Test 12/20/2023 No Access for Inspection JOHN KLARIN
Insulation 12/20/2023 Corrections Issued JOHN KLARIN
Gas Test 12/26/2023 Approved JOHN KLARIN
Sewer 12/26/2023 Approved JOHN KLARIN
Insulation 12/27/2023 Corrections Issued JOHN KLARIN
Insulation 1/4/2024 Approved JOHN KLARIN
Drywall Nailing 1/9/2024 Approved JOHN KLARIN
Shower Pan 1/31/2024 Corrections Issued JOHN KLARIN
Shower Pan 2/22/2024 Not Ready for Inspection BEN MOLSTAD
Shower Pan 3/5/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 8/14/2024 Corrections Issued BEN MOLSTAD
Final 8/14/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 8/14/2024 Approved BEN MOLSTAD
Green Building Final 8/14/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Approved BEN MOLSTAD
Service/Power Release 8/14/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 8/14/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 10/24/2024 Not Ready for Inspection ANTHONY EGSON
Final 10/24/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Final 10/24/2024 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 10/24/2024 Corrections Issued ANTHONY EGSON
Smoke Detectors 10/24/2024 Approved ANTHONY EGSON
Final 9/29/2025 Corrections Issued ANTHONY EGSON
Green Building Final 9/29/2025 Approved ANTHONY EGSON
Service/Power Release 9/29/2025 Not Ready for Inspection ANTHONY EGSON
Final 10/21/2025 Corrections Issued ANTHONY EGSON
Service/Power Release 10/21/2025 Not Ready for Inspection ANTHONY EGSON