10360 W ILONA AVE 90064
Certificate Information: 10360 W ILONA AVE 90064
- Application / Permit
- 22010-30000-02397
- Plan Check / Job No.
- B22WL01906
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 2/8/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | SERGIO SILVA |
| Corrections Issued | 6/8/2022 | SERGIO SILVA |
| Quality Review Completed | 6/30/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 9/22/2022 | SERGIO SILVA |
| Applicant returned to address corrections | 10/13/2022 | SERGIO SILVA |
| Plan Check Approved | 10/20/2022 | SERGIO SILVA |
| Building Plans Picked Up | 10/25/2022 | APPLICANT |
| Plan Check Approved | 2/1/2023 | SERGIO SILVA |
| Issued | 2/8/2023 | APPLICANT |
| CofO in Progress | 5/28/2025 | DANIEL VERA |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
| CofO Issued | 6/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/10/2022 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 8/14/2022 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 8/14/2022 | STEVEN JIN |
| Specific Plan | Cleared | 8/22/2022 | KEVIN ARUCAN |
| Trees in Parkway | Cleared | 8/30/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 9/3/2022 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | CATHERINE ADROVER |
| Permit | Cleared | 9/6/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 9/6/2022 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 9/22/2022 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 9/22/2022 | SERGIO SILVA |
Contact Information
| Contractor | A M Builders & Remodeling Inc; Lic. No.: 1030853-B | P O BOX 3347 WHITTIER, CA 90605 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
| Engineer | Hayrikian,, Arsham; Lic. No.: C91446 | 1732 CAMULOS AVE GLENDALE, CA 91208 |
| Engineer | Jahani,, Fereidoun; Lic. No.: C62875 | 3720 BLANCHE ST PASADENA, CA 91107 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Geologist | Minas,, Shant; Lic. No.: GEO8859 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Subgrade | 6/21/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/26/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 6/26/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 7/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| Structural Steel Frame | 7/24/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/8/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Barrier | 8/8/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 8/8/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Structural Steel Frame | 9/29/2023 | Partial Approval | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 9/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 10/3/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/24/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 12/15/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/20/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 1/8/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 1/8/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 1/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 1/8/2024 | Approved | STEPHANIE SWANSON |
| Deputy Other (see comments) | 1/9/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/9/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/11/2024 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 1/11/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Rough | 1/11/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 1/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/29/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/13/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/13/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 3/22/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 3/22/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 11/18/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 11/22/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/27/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | STEPHANIE SWANSON |
| Final | 1/28/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 1/28/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Service/Power Release | 1/28/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 1/28/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 4/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 4/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 4/17/2025 | Approved | DANIEL VERA |
| Final | 5/13/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Final | 5/27/2025 | Approved | DANIEL VERA |
| Final | 5/27/2025 | OK to Issue CofO | DANIEL VERA |
| Service/Power Release | 5/27/2025 | Approved | DANIEL VERA |