548 N HANLEY AVE 90049
Certificate Information: 548 N HANLEY AVE 90049
- Application / Permit
- 22010-30000-02302
- Plan Check / Job No.
- B22WL01818
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New one story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g) (800 SF max New Construction per State Law) NFPA 13D THRU OUT
- Permit Issued
- Issued on 7/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | RICHARD GARCIA |
| Corrections Issued | 5/13/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/24/2022 | JASON JANGADA |
| Building Plans Picked Up | 6/30/2022 | APPLICANT |
| Plan Check Approved | 7/1/2022 | AUNG SOE |
| Issued | 7/1/2022 | APPLICANT |
| CofO in Progress | 4/18/2023 | KEVIN SARGSYAN |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
| CofO Issued | 4/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | DINAH GARIN |
| Sewer availability | Cleared | 5/25/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 5/31/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 6/15/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/16/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/24/2022 | RICHARD GARCIA |
Contact Information
| Architect | Ungar,, Kenneth Joel; Lic. No.: C21777 | 1173 WESTBEND ROAD WESTLAKE VILLAGE, CA 91362 |
| Contractor | Owner-Builder | , |
| Engineer | Shah,, Kamal Rajendra; Lic. No.: C46200 | 28611 HASKELL CANYON RD SANTA CLARITA, CA 91390 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/20/2022 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/25/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/25/2022 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 8/23/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 8/23/2022 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/8/2022 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/8/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 9/8/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 9/8/2022 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 9/8/2022 | Approved | JUAN VALENZUELA |
| Insulation | 9/13/2022 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/14/2022 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 9/14/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/14/2022 | Approved | JUAN VALENZUELA |
| Insulation | 9/14/2022 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 10/7/2022 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/30/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 3/30/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 3/30/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/3/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 4/3/2023 | Approved | KEVIN SARGSYAN |
| Final | 4/17/2023 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 4/17/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 4/17/2023 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 4/17/2023 | Approved | KEVIN SARGSYAN |