3524 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3524 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22010-30000-02292
- Plan Check / Job No.
- B22WL01802
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 12' X 36' CABANA W/ POOL BATH, 10' X 25'-8" PORTION TO BE OPEN TRELLIS PATIO. ALL WORK PER ENG.
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2022 | JASON JANGADA |
| Corrections Issued | 7/11/2022 | JASON JANGADA |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Applicant returned to address corrections | 8/15/2022 | PINANK PATEL |
| Applicant returned to address corrections | 9/12/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/8/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/8/2022 | LUISANGEL VALENZUELA |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 5/15/2024 | JESUS PINEDA |
| Permit Finaled | 5/28/2024 | DANIEL ORRANTE |
| CofO Issued | 5/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2022 | DINAH GARIN |
| Sewer availability | Cleared | 7/22/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 8/10/2022 | CHRIS VONG |
| GPI Written Notices | Cleared | 8/15/2022 | JASON JANGADA |
| Grading Pre-Inspection | Cleared | 8/15/2022 | JASON JANGADA |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | AHMED AMARRAGY |
Contact Information
| Contractor | Refined Home Construction Inc; Lic. No.: 1001310-B | 113 N SAN VICENTE BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/14/2023 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 4/20/2023 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/31/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 5/31/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/31/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Gas Test | 7/5/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 7/5/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | JESUS PINEDA |
| Shower Pan | 7/10/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 7/13/2023 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 7/13/2023 | Approved | DAVID FEILER |
| Gas Test | 7/13/2023 | Partial Approval | DAVID FEILER |
| Green Building Rough | 7/13/2023 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 7/13/2023 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 7/13/2023 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 7/13/2023 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 7/21/2023 | Approved | JESUS PINEDA |
| Insulation | 7/21/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/21/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/1/2023 | Approved | JESUS PINEDA |
| Gas Test | 1/24/2024 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 1/29/2024 | No Access for Inspection | KENNETH NAGLE |
| ELECTRICAL-Final | 2/7/2024 | Approved | JESUS PINEDA |
| Gas Test | 2/7/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 2/7/2024 | Approved | JESUS PINEDA |
| Gas Test | 2/9/2024 | Approved | TEMISTOCLES CAAL |
| Final | 3/20/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 3/20/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 3/20/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 3/20/2024 | Approved | JESUS PINEDA |
| Final | 5/15/2024 | OK to Issue CofO | JESUS PINEDA |