3412 S BEETHOVEN ST 90066

Certificate Information: 3412 S BEETHOVEN ST 90066

Application / Permit
22010-30000-02133
Plan Check / Job No.
B22WL01583
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
new detached garage ***2 of 2 ***
Permit Issued
Issued on 9/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 TARIK SAOUD
Corrections Issued 5/9/2022 TARIK SAOUD
Quality Review Completed 5/11/2022 CHIHARU SUZUKI
Building Plans Picked Up 5/12/2022 APPLICANT
Plan Check Approved 9/6/2022 TARIK SAOUD
Issued 9/29/2022 APPLICANT
CofO in Progress 2/21/2024 JESUS RODRIGUEZ
Permit Finaled 2/21/2024 DANIEL ORRANTE
CofO Issued 2/21/2024 DANIEL ORRANTE
Permit Finaled 2/21/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/22/2022 ANTHONY MAINEZ
Low Impact Development Cleared 7/28/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 8/2/2022 ANTHONY MAINEZ
Specific Plan Cleared 8/4/2022 VALERIA CEJA
Grading Pre-Inspection Cleared 9/6/2022 TARIK SAOUD

Contact Information

Architect Winters,, Patrick Charles; Lic. No.: C22032 11410 BIONA DRIVE      LOS ANGELES, CA 90066
Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 6007 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 5/3/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 5/3/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/3/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/15/2023 Approved EVAN COOPER
Green Building Rough 5/15/2023 Approved EVAN COOPER
Interior/Exterior Lathing 5/15/2023 Partial Approval EVAN COOPER
Insulation 5/22/2023 Approved EVAN COOPER
ELECTRICAL-Final 12/14/2023 Approved JESUS RODRIGUEZ
Final 2/2/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 2/2/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 2/2/2024 Approved JESUS RODRIGUEZ
Final 2/20/2024 OK to Issue CofO JESUS RODRIGUEZ