742-742 1/2 E 48TH ST 90011
Certificate Information: 742-742 1/2 E 48TH ST 90011
- Application / Permit
- 22010-30000-01915
- Plan Check / Job No.
- B22WL01484
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached duplex (2) ADUs (315 sf each total 630 sf) per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | YASHAR EMAMI |
| Corrections Issued | 5/5/2022 | YASHAR EMAMI |
| Quality Review Completed | 5/9/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 5/11/2022 | APPLICANT |
| Applicant returned to address corrections | 8/10/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 11/17/2022 | YASHAR EMAMI |
| Plan Check Approved | 12/8/2022 | REZA HAGHIGHAT |
| Issued | 12/19/2022 | APPLICANT |
| CofO in Progress | 11/1/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 7/29/2022 | CHRISTOPHER ROCHA |
| DAS Clearance | Cleared | 8/12/2022 | YASHAR EMAMI |
| Construction near power lines | Cleared | 9/6/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/17/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/18/2022 | ABEL CASILLAS |
| Hydrant and Access approval | Cleared | 10/21/2022 | MATTHEW CRAIG |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Mr Build Home Improvement Company; Lic. No.: 439166-B | 12444 VICTORY BLVD UNIT 404 NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/26/2023 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 1/26/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 2/2/2023 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/20/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/3/2023 | No Access for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/6/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 4/6/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 4/6/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 4/26/2023 | Conditional Approval | BRENDAN MORELLI |
| Insulation | 5/2/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 5/9/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 5/9/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 5/9/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/9/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Rough-Elec/Plmb/HVAC | 5/9/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 8/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 9/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 9/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/10/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/31/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 10/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/31/2023 | Approved | ALEJANDRO DE ARTOLA |