742-742 1/2 E 48TH ST 90011

Certificate Information: 742-742 1/2 E 48TH ST 90011

Application / Permit
22010-30000-01915
Plan Check / Job No.
B22WL01484
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached duplex (2) ADUs (315 sf each total 630 sf) per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 12/19/2022
Issuing Office
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 YASHAR EMAMI
Corrections Issued 5/5/2022 YASHAR EMAMI
Quality Review Completed 5/9/2022 CHIHARU SUZUKI
Building Plans Picked Up 5/11/2022 APPLICANT
Applicant returned to address corrections 8/10/2022 YASHAR EMAMI
Applicant returned to address corrections 11/17/2022 YASHAR EMAMI
Plan Check Approved 12/8/2022 REZA HAGHIGHAT
Issued 12/19/2022 APPLICANT
CofO in Progress 11/1/2023 ALEJANDRO DE ARTOLA
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/28/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/29/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 7/29/2022 CHRISTOPHER ROCHA
DAS Clearance Cleared 8/12/2022 YASHAR EMAMI
Construction near power lines Cleared 9/6/2022 RIDWAN HARDY
Low Impact Development Cleared 10/17/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/18/2022 ABEL CASILLAS
Hydrant and Access approval Cleared 10/21/2022 MATTHEW CRAIG

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Mr Build Home Improvement Company; Lic. No.: 439166-B 12444 VICTORY BLVD UNIT 404      NORTH HOLLYWOOD, CA 91606

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/26/2023 Partial Approval SCOTT FINNILA
Underground Mechanical 1/26/2023 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 2/2/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 3/20/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/20/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 3/20/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 3/20/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 3/20/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/3/2023 No Access for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 4/6/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Partial Approval BRENDAN MORELLI
Green Building Rough 4/6/2023 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 4/6/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 4/17/2023 Partial Approval BRENDAN MORELLI
Insulation 4/26/2023 Conditional Approval BRENDAN MORELLI
Insulation 5/2/2023 Approved BRENDAN MORELLI
Drywall Nailing 5/9/2023 Approved BRENDAN MORELLI
Green Building Rough 5/9/2023 Approved BRENDAN MORELLI
HVAC-Rough 5/9/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 5/9/2023 Not Ready for Inspection BRENDAN MORELLI
Rough-Elec/Plmb/HVAC 5/9/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 8/9/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/9/2023 Approved ALEJANDRO DE ARTOLA
Green Building Final 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/9/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 8/9/2023 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 8/9/2023 Approved ALEJANDRO DE ARTOLA
Sewer 8/21/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 9/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 9/22/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 10/10/2023 Approved ALEJANDRO DE ARTOLA
Green Building Final 10/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 10/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/13/2023 Approved ALEJANDRO DE ARTOLA
Final 10/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/13/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/13/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/13/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/31/2023 Approved ALEJANDRO DE ARTOLA
Final 10/31/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Gas Test 10/31/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/31/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/31/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/31/2023 Approved ALEJANDRO DE ARTOLA